contract agreement · K-2
Discussion and Consideration of Pay Application #10 – Miron Construction – Tiffin Recreation Center Project – Motion to Approve — K.2
Page 1 of 17
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-2
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: April 17, 2026
AGENDA ITEM: Discussion and Consideration of Pay Application #10 – Miron Construction –
Tiffin Recreation Center Project
ACTION: Motion
Background
The City of Tiffin entered into an agreement with Miron Construction Co., Inc. for construction
of the Community Recreation Center located at 105 S. Park Road. The project is currently under
construction, with work progressing across multiple building systems including structural,
mechanical, electrical, and interior components.
Pay Application No. 10 represents progress through February 28, 2026 and reflects the value of
work completed and materials stored on-site to date, as reviewed and certified by the project
architect.
Key figures include:
• Original Contract Amount: $12,435,142.00
• Net Change Orders: ($1,042,001.88)
• Revised Contract Amount: $11,393,140.12
• Total Completed to Date: $5,699,348.90
• Retainage Held: $284,967.45
• Previous Payments: $4,891,111.62
• Current Payment Requested: $523,269.83
The project is approximately 50% complete based on total work completed to date.
Work completed this period includes continued progress on structural systems,
mechanical/electrical rough-ins, and building enclosure components. Materials stored on-site and
included in this pay application (as shown in the attached documentation and photos) have been
verified and are eligible for payment in accordance with contract provisions.
The application has been reviewed and certified by Atura Architecture, confirming that the work
completed is in accordance with the contract documents and that the payment amount is
appropriate.
Staff Recommendation
Staff recommends approval of Pay Application No. 10 to Miron Construction Co., Inc. in the
amount of $523,269.83 for work completed through February 28, 2026.
ATTACHMENTS: Pay Application
1
Sources
- revize: K.2 (8ML5xkHm6nq6U17AdBvw3UCIhe3sAu.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Pay Application #10 – Miron Construction – Tiffin...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.