Text from the PDF text layer; check the PDF for anything that matters. ENGINEER'S OPINION OF PROBABLE COSTS
ROBERTS FERRY ROAD & VILLAGE DRIVE TRAFFIC SIGNAL IMPROVEMENTS
TIFFIN, IOWA
DATE: 4/13/2026 Estimate Year 2026
MSA PROJECT #: 13603027 Construction Year 2026
Project Total
ITEM NO. SUDAS NO. DESCRIPTION UNIT UNIT PRICE QUANTITY TOTAL PRICE
Division 2: Earthwork
1 2010-D-1 Topsoil, On-site CY $ 100 8 $ 800
Division 6: Structures for Sanitary and Storm Sewers
2 6010-E-1 Manhole Adjustment, Minor EA $ 1,800 2 $ 3,600
Division 7: Streets and Related Work
3 7030-A-1 Removal of Sidewalk SY $ 15 40.0 $ 600
4 7030-E Sidewalk, PCC, 4 in. SY $ 30 120.0 $ 3,600
5 7030-E Sidewalk, PCC, 6 in. SY $ 80 75.0 $ 6,000
6 7030-G Detectable Warning SF $ 50 64 $ 3,200
7 7040-A Full Depth Patches, PCC, 10 in. SY $ 150 90.0 $ 13,500
Division 8: Traffic Control
8 8010-A Traffic Signal LS $ 345,000 1 $ 345,000
9 8020-C Painted Pavement Markings, Durable STA $ 5 8 $ 40
10 8020-G Painted Symbols and Legends, Durable EA $ 500 10 $ 5,000
11 8020-K Pavement Markings Removed STA $ 5 5.9 $ 30
12 8020-L Symbols and Legends Removed EA $ 160 9 $ 1,440
13 8030-A Temporary Traffic Control LS $ 10,000 1 $ 10,000
14 8040-B Traffic Signs SF $ 25 73.75 $ 1,844
Division 9: Site Work and Landscaping
15 9010-A Conventional Seeding, Seeding, Fertilizing, and Mulching, Type 1 LS $ 2,000 1 $ 2,000
16 9040-F-1 Wattle LF $ 9 150 $ 1,350
17 9040-F-2 Wattle, Removal LF $ 3 150 $ 450
18 9040-T-1 Inlet Protection Device, Surface-Applied EA $ 110 4 $ 440
Division 11: Miscellaneous
19 11,020-A Mobilization LS $ 32,000 1 $ 32,000
ESTIMATED CONSTRUCTION SUBTOTAL $ 430,893
Contingency 10% $ 43,100
Inflation 5% per year $ -
ESTIMATED CONSTRUCTION COST (2026) $ 473,993
Estimated Grant/Loan Administration $ -
Estimated Legal Fees $ -
Estimated Property Acquisition $ -
Estimated Design Engineering $ 58,525
Estimated Construction Engineering 10% $ 47,400
TOTAL ESTIMATED PROJECT COST: $ 580,000
Disclaimers & Assumptions
This opinion of probable cost is approximate. Actual construction bids may vary significantly from this opinion due to timing of bids, constructual schedule restraints, labor rate
1
increases, material increases, or other factors beyond the control of the engineer.
G:\13\13603\13603027\Cost Estimating\13603027 Preliminary Cost Estimate.xlsm Completed By:
Sources
- revize: I.2 (vzm2HJHuQo9g180NPGQjV4WBcYUyGe.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: I-2 Resolution No. 2026-027 – A Resolution Setting the Date of May 19, 2026, for a Public...
Data last updated October 17, 2026. Built from the archive's documents; see how the data is built.