Text from the PDF text layer; check the PDF for anything that matters.Contract Summary
Contract Summary Construction Manager Contingency Summary Owner Contingency Summary
Original Contract Amount: $12,435,142.00 CMaR Contingency Amount: $567,585.00 Owner Contingency Amount: $0.00
Change Orders to Date: -$801.62 Change Orders to Date: -$173,991.91 Change Orders to Date: $225,451.17
Current Contract Value: $12,434,340.38 CMaR Contingency Value: $393,593.09 Owner Contingency Value: $225,451.17
Current Scope Revisions
CMaR Owner
Allowance Contingency Contingency Estimated Cost
Description Number Date Submitted Status Item? Item? Item? Impact
Project Contingency PCI's June 2025 thru
November 2025 001-016 11/30/2025 Approved Yes -$56,426.39
Owner Contingency PCI's June 2025 thru
November 2026 001-016 11/30/2025 Approved Yes -$125,040.83
Add backing panel to exterior signage 024 2/17/2026 Approved Yes -$14,800.00
Change AF-2 from 20% fleck color to 30% fleck
color 025 2/17/2026 Approved Yes -$2,061.20
Repair broken conduit 026 2/23/2026 Approved Yes -$801.62
RFI#23 2nd Floor Deck Edging 027 3/4/2026 Approved Yes -$14,222.20
Remake Exterior Duct Work due to Steel
Column Conflict 028 3/5/2026 Approved Yes -$2,160.00
Change LVT flooring collection. Thicker wear
layer and longer warranty 029 4/6/2026 Approved Yes -$1,847.00
ASI-16 Updated WAPs and Camera quantities
and locations 030 4/9/2026 In Review Yes -$16,336.75
Additional labor and material costs beyond
signage blocking allowance 031 4/22/2026 Approved Yes -$12,897.14
ASI-15 SW Sidewalk Change 032 4/22/2026 In Review Yes 2 Options
Extend NE mechanical pad to accommodate
gate access 034 4/28/2026 Approved Yes -$2,607.69
Box around portal frames to close off beam
pockets 035 4/28/2026 Approved Yes -$1,858.67
Owner Progress Report | 250120 April 2026 Miron Construction Co., Inc. | 10
Sheets in this document
- p. 21 N88 · Easement Exhibit · MMS Consultants · Park Place City Center - Part Two, Phase Four
- p. 29 1 · Rezoning Exhibit · MMS Consultants
- p. 70 Title Sheet · MSA
- p. 71 CP1 · Elevation · MSA · Roberts Ferry RD & Village DR Signal Improvements
- p. 72 Removal Plan · MSA · Village DR
- p. 73 Traffic Control Plan · MSA · Roberts Ferry RD & Village DR Signal Improvements
- p. 74 Pavement Marking Plan · MSA · Village DR
- p. 75 Point Number & Elevation · MSA
- p. 76 Curb Ramp Details · MSA · Roberts Ferry RD & Village DR Signal Improvements
- p. 85 1 West Elevation
- p. 89 Final Plat · MMS Consultants · Park Place City Center - Part One, Phase Three
- p. 162 City of Tiffin FY 25-26 Town Hours by Month (chart; data on p. 161)
- p. 165 City of Tiffin FY 25-26 (chart; data on p. 163)
- p. 200 1st Floor Overhead Rough In · Electrical