contract agreement · K-2
Discussion and Consideration of Pay Application #12 – Miron Construction – Tiffin Recreation Center Project – Motion to Approve — K.2
Page 5 of 41
Text from the PDF text layer; check the PDF for anything that matters. Miron Construction Co., Inc.
CONTINUATION SHEET AIA DOCUMENT G703
Page: 4
AIA DOCUMENT G702, APPLICATION AND CERTIFICATE FOR PAYMENT, containing
Contractor's signed Certification is attached. APPLICATION NUMBER: 12
In tabulation below, amounts are stated to the nearest cent. APPLICATION DATE: 04/28/2026 INVOICE NO.:
Use Column I on Contracts where variable relainage for line items may apply. PERIOD TO: 04/30/2026 250120-0012
PROJECT NO: 250120
A B C D E F G H I
SCHEDULED VALUE WORK COMPLETED (D+E)
TOTAL
MATERIAL
FROM COMPLETED PER- BALANCE
ITEM NO. DESCRIPTION OF WORK CHANGE PRESENTLY RETAINAGE
ORIGINAL CURRENT PREVIOUS THIS PERIOD AND STORED %(G/c TO FINISH
ORDERS STORED
APPLICATION TO DATE
215 Landscaping Allowance 75,000.00 -75,000.00 0.00 0.00 0.00 0.00 0.00 0 o.oc 0.00
220 Unreleased Add #3 Allowance 10,000.00 -10,000.00 0.00 0.00 0.00 0.00 0.00 0 o.oc 0.00
Project Total 12,435,142.00 -1,042,001.88 11,393,140.12 6,399,298.66 585,406.76j 196, 170.00 7,180,875.42 63 4,212,264.70 359,043.78
AIA DOCUMENT G703 - APPLICATION AND CERTIFICATE FOR PAYMENT
THE AMERICAN INSTITUTE OF ARCHITECTS 1735 NEW YORK AVENUE NW WASHINGTON DC 20006
I
Sources
- revize: K.2 (B2fPpimpwMa7H9wwbMqqtqg1yqDQuS.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Pay Application #12 – Miron Construction – Tiffin...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.