Discussion and Consideration of Pay Application #12 – Miron Construction – Tiffin Recreation Center Project – Motion to Approve — K.2
Page 3 of 41
Text from the PDF text layer; check the PDF for anything that matters. Miron Construction Co., Inc.
CONTINUATION SHEET AIA DOCUMENT G703
Page: 2
AIA DOCUMENT G702, APPLICATION AND CERTIFICATE FOR PAYMENT, containing
Contractor's signed Certification is attached. APPLICATION NUMBER: 12
In tabulation below, amounts are stated to the nearest cent. APPLICATION DATE: 04/28/2026 INVOICE NO.:
Use Column I on Contracts where variable retainage for line items may apply.
PERIOD TO: 04/30/2026 250120-0012
PROJECT NO: 250120
A B C D E F G H I
SCHEDULED VALUE WORK COMPLETED (D+E)
TOTAL
MATERIAL
ITEM NO. DESCRIPTION OF WORK FROM COMPLETED PER- BALANCE
CHANGE PRESENTLY RETAINAGE
ORIGINAL . ORDERS
CURRENT PREVIOUS
APPLICATION
THIS PERIOD STORED
AND STORED %(G/C
TO DATE
TO FINISH
005 General Conditions 503,136.00 6,000.00 509,136.00 298,737.00 37,446.00 0.00 336,183.00 66 172,953.0( 16,809.15
010 General Requirements 206,878.00 0.00 206,878.00 106,555.37 30,377.40 0.00 136,932.77 66 69,945.2 6,846.69
015 Construction Manager Contingency 567,585.00 -156,628.41 410,956.59 0.00 0.00 0.00 0.00 0 410,956.5 0.00
016 Owner Contingency 0.00 225,451.17 225,451.17 0.00 0.00 0.00 0.00 0 225,451.17 0.00
020 Construction Fee 500,822.00 -42,001.00 458,821.00 382,953.67 20,547.78 0.00 403,501.45 88 55,319.5 20,175.01
025 Preconstruction Services 10,000.00 0.00 10,000.00 10,000.00 0.00 0.00 10,000.00 100 0.0( 500.00
030 Railroad Insurance 5,050.00 0.00 5,050.00 5,050.00 0.00 0.00 5,050.00 100 0.0( 252.50
035 Cast In Place Concrete 813,985.00 87,587.70 901,572.70 734,717.55 42,285.05 0.00 777,002.60 86 124,570.1 38,850.13
040 Masonry 344,553.00 -166,080.78 178,472.22 172,472.22 0.00 0.00 172,472.22 97 6,000.0( 8,623.61
045 Steel Fabrication and Erection 987,710.00 108,545.80 1,096,255.80 1,019,984.75 11,255.80 0.00 1,031,240.55 94 65,015.2 51,562.04
050 General Trades 327,150.00 71,718.84 398,868.84 39,504.30 45,000.00 0.00 84,504.30 21 314,364.5 4,225.22
055 Rolling Doors and Shutters 6,890.00 1,870.00 8,760.00 0.00 0.00 0.00 0.00 0 8,760.0( 0.00
060 Alum Windows, Entrances, Glass/Glazing 611,932.00 -222,632.00 389,300.00 182,815.00 40,790.00 0.00 223,605.00 57 165,695.0( 11,180.25
065 Gypsum Board Systems 320,909.00 -107,219.00 213,690.00 0.00 39,500.00 0.00 39,500.00 18 174,190.0 1,975.00
070 Tile 13,129.00 2,934.00 16,063.00 0.00 0.00 5,665.00 5,665.00 35 10,398.0( 283.25
075 Suspended Acoustical Ceiling and Panels 117,427.00 -27,246.00 90,181.00 18,169.00 9,888.00 0.00 28,057.00 31 62,124.0( 1,402.85
080 Resilient Athletic Flooring 269,255.00 -41,205.00 228,050.00 818.00 7,702.00 115,575.00 124,095.00 54 103,955.0( 6,204.75
085 Wood Athletic Flooring 240,000.00 -40,307.00 199,693.00 9,985.00 0.00 0.00 9,985.00 5 189,708.0( 499.25
090 Resilient Flooring, Base and Carpet 67,829.00 -44,372.00 23,457.00 0.00 0.00 0.00 0.00 0 23,457.0 0.00
095 Painting and Wall Covering 161,504.00 -72,450.50 89,053.50 0.00 0.00 0.00 0.00 0 89,053.5( 0.00
100 Building Signage 80,097.00 20,203.00 100,300.00 0.00 0.00 50,150.00 50,150.00 50 50,150.0( 2,507.50
105 Athletic Equipment 300,600.00 12,745.00 313,345.00 15,667.00 0.00 0.00 15,667.00 5 297,678.0( 783.35
Sources
- revize: K.2 (B2fPpimpwMa7H9wwbMqqtqg1yqDQuS.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Pay Application #12 – Miron Construction – Tiffin...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.