Discussion and Consideration of Pay Application #12 – Miron Construction – Tiffin Recreation Center Project – Motion to Approve — K.2
Page 1 of 41
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-2
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: May 15, 2026
AGENDA ITEM: Discussion and Consideration of Pay Application #12 – Miron Construction
– Tiffin Recreation Center Project – Motion to Approve
ACTION: Motion
Background
The City of Tiffin continues construction of the Tiffin Recreation Center in partnership with
Miron Construction Co., Inc.
Pay Application No. 12 covers work completed through April 30, 2026, and reflects ongoing
progress across multiple project components, including structural systems, interior work,
mechanical systems, and site utilities.
This pay application reflects continued substantial progress on the Recreation Center project.
Key work activities during this period include:
• Advancement of structural and exterior systems (steel, masonry, metal building
components)
• Continued installation of mechanical, electrical, and plumbing systems
• Interior build-out progress, including flooring, ceilings, and specialty equipment
• Site work and utilities nearing completion in some areas
Several line items are approaching completion (e.g., concrete, steel, utilities), while others such
as interior finishes, athletic flooring, and site improvements are ongoing.
The application has been reviewed and is consistent with the project schedule and percentage of
completion. Retainage continues to be withheld per contract requirements.
Recommendation
Staff recommends approval of Resolution No. 2026-038, approving the final plat for Park Place
City Center – Part One, Phase Four, subject to the outlined conditions.
ATTACHMENTS: Pay Application
1
Sources
- revize: K.2 (B2fPpimpwMa7H9wwbMqqtqg1yqDQuS.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Pay Application #12 – Miron Construction – Tiffin...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.