Text from the PDF text layer; check the PDF for anything that matters. BID TABULATION
PROJECT: Roberts Ferry Road & Village Drive Traffic Signal Improvements PROJECT NO.: 13603027
OWNER: City of Tiffin BID DATE: May 14, 2026
Neumiller Electric Price Industrial Electric Inc. Van Maanen Electric, Inc. KW Electric
251 Greenfield Dr. 405 N Troy Rd 500 Iowa Speedway Drive 1127 Lincoln Street
Tiffin, IA 52340 Robins, IA 52328 Newton, IA 50208 Cedar Falls, IA 50613
ITEM ITEM EST'D UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL
NO. DESCRIPTION QNTY UNITS PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE
Division 2: Earthwork
1 Topsoil, On-site 8 CY $ 100.00 $ 800.00 $ 250.00 $ 2,000.00 $ 355.00 $ 2,840.00 $ 200.00 $ 1,600.00
Division 6: Structures for Sanitary and Storm Sewers
2 Manhold Adjustment, Minor 2 EA $ 2,000.00 $ 4,000.00 $ 600.00 $ 1,200.00 $ 1,600.00 $ 3,200.00 $ 1,500.00 $ 3,000.00
Division 7: Streets and Related Work
3 Removal of Sidewalk 40 SY $ 15.00 $ 600.00 $ 22.00 $ 880.00 $ 50.00 $ 2,000.00 $ 45.00 $ 1,800.00
4 Sidewalk, PCC, 4-in. 120 SY $ 60.00 $ 7,200.00 $ 66.00 $ 7,920.00 $ 65.00 $ 7,800.00 $ 65.00 $ 7,800.00
5 Sidewalk, PCC 6-in. 75 SY $ 70.00 $ 5,250.00 $ 110.00 $ 8,250.00 $ 75.00 $ 5,625.00 $ 75.00 $ 5,625.00
6 Detectable Warnings 64 SF $ 70.00 $ 4,480.00 $ 55.00 $ 3,520.00 $ 75.00 $ 4,800.00 $ 75.00 $ 4,800.00
7 Full Depth Patches, PCC, 10-in. 90 SY $ 215.00 $ 19,350.00 $ 154.00 $ 13,860.00 $ 235.00 $ 21,150.00 $ 225.00 $ 20,250.00
Division 8: Traffic Control
8 Traffic Signal 1 LS $ 277,000.00 $ 277,000.00 $ 340,000.00 $ 340,000.00 $ 318,627.25 $ 318,627.25 $ 346,700.00 $ 346,700.00
9 Painted Pavement Markings, Durable 8 STA $ 850.00 $ 6,800.00 $ 797.50 $ 6,380.00 $ 910.00 $ 7,280.00 $ 1,150.00 $ 9,200.00
10 Painted Symbols and Legends, Durable 10 EA $ 300.00 $ 3,000.00 $ 165.00 $ 1,650.00 $ 325.00 $ 3,250.00 $ 475.00 $ 4,750.00
11 Pavement Markings Removed 5.9 STA $ 200.00 $ 1,180.00 $ 495.00 $ 2,920.50 $ 220.00 $ 1,298.00 $ 425.00 $ 2,507.50
12 Symbols and Legends Removed 9 EA $ 150.00 $ 1,350.00 $ 137.50 $ 1,237.50 $ 165.00 $ 1,485.00 $ 105.00 $ 945.00
13 Temporary Traffic Control 1 LS $ 8,500.00 $ 8,500.00 $ 6,600.00 $ 6,600.00 $ 8,025.00 $ 8,025.00 $ 9,250.00 $ 9,250.00
14 Traffic Signs 73.75 SF $ 25.00 $ 1,843.75 $ 55.00 $ 4,056.25 $ 75.00 $ 5,531.25 $ 42.00 $ 3,097.50
Division 9: Site Work and Landscaping
Conventional Seeding, Seeding Fertilizing and
15 1 LS $ 2,500.00 $ 2,500.00 $ 2,750.00 $ 2,750.00 $ 3,000.00 $ 3,000.00 $ 2,625.00 $ 2,625.00
Mulching, Type 1
16 Wattle 150 LF $ 3.00 $ 450.00 $ 2.00 $ 300.00 $ 5.50 $ 825.00 $ 3.15 $ 472.50
17 Wattle, Removal 150 LF $ 1.00 $ 150.00 $ 0.50 $ 75.00 $ 1.25 $ 187.50 $ 1.00 $ 150.00
18 Intake Protection Device, Surface-Applied 4 EA $ 100.00 $ 400.00 $ 250.00 $ 1,000.00 $ 450.00 $ 1,800.00 $ 105.00 $ 420.00
Division 11: Miscellaneous
19 Mobilization 1 LS $ 23,000.00 $ 23,000.00 $ 15,000.00 $ 15,000.00 $ 25,000.00 $ 25,000.00 $ 5,000.00 $ 5,000.00
TOTAL BASE BID: $ 367,853.75 $ 419,599.25 $ 423,724.00 $ 429,992.50
For updated bidding information visit us at www.msa-ps.com
1 of 1
Sources
- revize: I.3 (1G17AxbtJP4zH7soWXwUd9zaaSE87G.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: I-3 Resolution No. 2026-036 – A Resolution to Award the Bid for the Village Drive and...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.