Text from the PDF text layer; check the PDF for anything that matters. Miron Construction Co., Inc.
CONTINUATION SHEET AIA DOCUMENT G703
Page: 4
AIA DOCUMENT G702, APPLICATION AND CERTIFICATE FOR PAYMENT, containing
Contractor's signed Certification is attached. APPLICATION NUMBER: 13
In tabulation below, amounts are stated to the nearest cent. APPLICATION DATE: 05/26/2026 INVOICE NO.:
Use Column I on Contracts where variable retainage for line items may apply. PERIOD TO: 05/31/2026 250120-0013
PROJECT NO: 250120
A B C D E F G H I
SCHEDULED VALUE WORK COMPLETED (D+E)
TOTAL
MATERIAL
FROM COMPLETED PER- BALANCE
ITEM NO. DESCRIPTION OF WORK CHANGE PRESENTLY RETAINAGE
ORIGINAL CURRENT PREVIOUS THIS PERIOD AND STORED %(G/C TO FINISH
ORDERS STORED
APPLICATION TO DATE
215 Landscaping Allowance 75,000.00 -75,000.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00
220 Unreleased Add #3 Allowance 10,000.00 -10,000.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00
Project Total 12,435,142.00 -1,042,001.88 11,393,140.12 7,180,875.42 494,290.82 0.00 7,675, 166.24 67 3,717,973.88 383,758.32
AIA DOCUMENT G703 - APPLICATION AND CERTIFICATE FOR PAYMENT
THE AMERICAN INSTITUTE OF ARCHITECTS 1735 NEW YORK AVENUE NW WASHINGTON DC 20006
Sources
- revize: K.6 (9nYBQpNb0mBbJTakJ3JiBMzXQE0OiK.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-6 Discussion and Consideration of Pay Application #13 – Miron Construction – Tiffin...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.