contract agreement · K-2
Discussion and Consideration of Change Order #16 – Boomerang Corporation – North Park Road Improvements Project – Motion to Approve — K.2
Page 3 of 5
Text from the PDF text layer; check the PDF for anything that matters. connection to the existing 30in RCP. Removal of existing 30in RCP and installation of new 30in RCP were covered under existing bid items, however a bid item to account for the
extra work necessary to connect to existing storm sewer was omitted at the time of bid.
C-Settlement for cost(s) of change
8230: Agreed unit price.
D-Justification for cost(s)
8230: Unit price ($2500.00/EA) is above the average unit bid price of the same item ($1770.42/EA) and below the maximum unit bid price ($4200.00/EA) when compared with a
Bid Tab analysis of bid prices for the item from July 2025 to May 2026.
E-contract time adjustment
None. This change has no impact on the controlling item of work.
New Items
Line Number Item ID Unit Quantity Unit Price Extension
Section: 0001 - STP-U-7662(615)--70-52, ROADWAY ITEMS
8230 2435-0700020 EACH 3.000 $2,500.000 $7,500.00
CONNECTION TO EXISTING INTAKE
Reason: (3) connections to existing needed for I-28 & I-29 that were previously omitted in the bid items but included in the plans.
Funding Details
52-7662-615-CAT-1 ROADWAY ITEMS 3.000 $2,500.000 $7,500.00
1 item Total: $7,500.00
Change Order Details: 05/07/2026
52-7662-615 Page 2 of 3
Sources
- revize: K.2 (7Wi8X6S26cbSL6rfw8QgXAcmM4whut.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration of Change Order #16 – Boomerang Corporation – North Park...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.