8250: Agreed unit price. Unit Price ($330.00/EA) is significantly below the average unit bid price of the same item ($521.32/EA) when compared with the Summary of Awarded Contract Unit Prices for the item from January 2025 to July 2026. 8260: Agreed unit price. Unit price ($2,000/EA) could not be compared with the Summary of Awarded Contract Unit Prices for the item from February 2023 to June 2026 for Extra Work Type C-1 Connection, as no recent bids for this item have been recorded. It is acknowledged that the lack of bids in the Summary may reflect low quantities, and so we could consider the bid price of the existing bid item "Connection to Existing Intake" which is ($2,500/EA), and comparable work. The Agreed unit price ($2,000/EA) is below the Connection to Existing Intake Unit Price. E-contract time adjustment These changes would add 2 days due to the impact to the controlling item of work. Increases/Decreases Line Number Item ID Unit Unit Price Current Change Revised Quantity Amount Quantity Amount Quantity Amount Section: 0001 - STP-U-7662(615)--70-52, ROADWAY ITEMS 0080 2115-0100000 CY $43.000 4,691.000 $201,713.00 88.890 $3,822.27 4,779.890 $205,535.27 MODIFIED SUBBASE Funding Details 52-7662-615-CAT-1 ROADWAY ITEMS 4,691.000 $201,713.00 88.890 $3,822.27 4,779.890 $205,535.27 52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 0.000 $0.00 0.000 $0.00 0.000 $0.00 52-7662-615-CAT-3 NON-PARTICIPATING 0.000 $0.00 0.000 $0.00 0.000 $0.00 1 item Totals $201,713.00 $3,822.27 $205,535.27 Change Order Details: 07/23/2026 52-7662-615 Page 3 of 5

Sources

  • revize: Agenda packet (packet_2026-08-05_fc636f94-ba1c-4f50-b3a2-3fb8ea3ce48f.pdf) — where it was found ↗ first seen Oct 12, 2026

This document's details as JSON

Data last updated October 18, 2026. Built from the archive's documents; see how the data is built.