Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
July 31, 2026
PROJECT UPDATE
NORTH PARK ROAD IMPROVEMENTS – JAMES WATTERS
In early July, the builder for the property on the Southwest corner of North Park Road and Mopar Drive
asked to verify the location of a sanitary service to the property. City Staff worked to locate the service stub
and determined that the stub had not been installed with the sanitary sewer along the east side of North
Park Road. A change order to the North Park Road project was approved for the completion of that work
before paving began.
This work and all other underground utility work have been completed. The next major construction item
planned is the Oak Hill entrance, trail, and sidewalk paving. Roadway paving is scheduled to begin in August.
It is not anticipated that the roadway paving will be completed before the start of the school year.
Simon Downs and Thomas Blair will be on-site for the first week of August as substitute inspectors.
ROBERTS FERRY ROAD SHOULDER WIDENING – ANDREW INHELDER
The City has the desire to widen the shoulder on the eastern side of Roberts Ferry Road, from Village Drive
to the Trail to the north. The shoulder will narrow at the bridge as no bridge widening is planned as part of
the project. MSA has surveyed the area and have begun preliminary design to widen the shoulder.
US 6 AND DEER VIEW AVE TRAFFIC SIGNAL DESIGN – JAMES WATTERS
The City is upgrading the temporary signals at US 6 and Deer View Ave to permanent signals. Survey has
been scheduled and will be performed along with a kickoff meeting to be held with the City after survey is
completed. Traffic turning movement count will be scheduled for after school starts, likely sometime in
September to aid in the design of the improvements. Trail and stormwater improvements are anticipated
as part of the design in this area.
PROJECT UPDATE
Page 2 of 5
Sources
- revize: L-2 (DrKdNwm0f5CoW9LyYbJp8jFQLaqtSf.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-2 City Engineer's Report
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.