contract agreement · E-7
Approval of Change Order #17 – Boomerang Corporation - North Park Road Improvements — E-7
Page 3 of 7
Text from the PDF text layer; check the PDF for anything that matters. B-Reason for Change
8240: Add 8in truss pipe for a sanitary service to Daytona Estates at the SW corner of Mopar Drive and North Park Rd (see sheet M.12). It was recently discovered that an 8-inch
sanitary sewer service, which was intended to be installed as part of a previous project, was never constructed. The City wishes to install this sanitary sewer while construction is
still in progress and while the road is still unpaved.
8250: Subdrain on the current phase has already been installed prior to discovering the missing sanitary service. The Subdrain Repair bid item includes the removal and
replacement of any subdrain impacted by the excavation required to install the sanitary sewer service.
8260: Storm sewer pipe on the current phase has already been installed. The proposed change order sanitary will cross under storm pipe P-30, to safely construct the trench this
pipe will be cut out and replaced. The Type C-1 connection bid item includes the sawcutting on the RCP pipe, and pouring (2) two collars back per SW-211.
0080: Because the roadway has already been constructed with Modified Subbase, an overrun of the existing Modified Subbase bid item has been included for the removal and
reinstallation of the roadway section impacted by this work. This work consists of carefully removing and stockpiling as much of the existing Modified Subbase as possible without
contaminating the material during excavation, then reinstalling the salvaged Modified Subbase after the trench has been properly backfilled. Compensation for this item will be
based on the actual field-measured quantity, with the measured volume doubled to account for both the removal and reinstallation of the Modified Subbase. The estimated quantity
of 88.89 CY is provided solely for bidding purposes and will be adjusted to reflect the actual quantity required to complete the work.
C-Settlement for cost(s) of change
8240: Agreed unit price.
8250: Agreed unit price.
8260: Agreed unit price.
0080: Contract unit bid price.
D-Justification for cost(s)
8240: Agreed unit price. Unit Price ($125.00/LF) could not be compared with the Summary of Awarded Contract Unit Prices for the item from February 2023 to June 2026 for 8in
sanitary service, as no recent bids for this item have been recorded. It is acknowledged that the lack of bids in the Summary may reflect low quantities, and so we could consider
the bid prices of 4 IN. and 6 IN. in the Summary. The Agreed unit price ($125.00/LF) is above both the 4 IN. and 6 IN. unit prices when compared with the Summary of Awarded
Contract Unit Prices for the item(s) from January 2026 to July 2026.
Change Order Details: 07/23/2026
52-7662-615 Page 2 of 5
Sources
- revize: E-7 (hkU9EUTzPKEBUVRiA8zrx6KvSLAz5J.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-7 Approval of Change Order #17 – Boomerang Corporation - North Park Road Improvements
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.