contract agreement · E-4
Approval of Pay Application #15 – Miron Construction – Community Recreation Center — E-4
Page 1 of 5
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # E-4
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: July 30, 2026
AGENDA ITEM: Approval of Pay Application #15 – Miron Construction – Community
Recreation Center
ACTION: Motion
Background
Miron Construction Co., Inc. has submitted Pay Application No. 15 for work completed on the
Tiffin Community Recreation Center through July 31, 2026. This pay application reflects
construction progress completed during the current billing period and has been reviewed by the
project architect, Atura Architecture.
As of Pay Application No. 15:
• The project is approximately 79% complete.
• Construction activity during this payment period totaled $778,008.81.
• Major work completed during the period included continued progress on:
o Metal Building Systems
o Electrical
o Athletic Equipment
o Steel Fabrication and Erection
o Elevators
o General Trades
o Landscaping
o Interior finishes including ceilings, painting, flooring, and mechanical systems.
Recommendation
Staff recommends approval of Pay Application No. 15 in the amount of $739,108.37 to Miron
Construction Co., Inc. for work completed on the Tiffin Community Recreation Center through
July 31, 2026, subject to the architect's certification.
ATTACHMENTS: Pay Application
1
Sources
- revize: E-4 (o9y6IupeZ2xHF5fWpaDfXK2wsZ49oy.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-4 Approval of Pay Application #15 – Miron Construction – Community Recreation Center
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.