Discussion and Review of Potential Funding Opportunities through the IDOT for Trail and Pedestrian Tunnel Improvements — Hwy 6 Ped Underpass Options & Cost Estimate
Page 1 of 3
Text from the PDF text layer; check the PDF for anything that matters. Orange Route Yellow Route (Option 6, 600 FT
(Option 4, 700 FT) - off page)
Green route (Option 3, 1,500
FT) 10' trail from Croell Avenue to N.
Route 10' trail
through Kimberlite St
10' trail installed adjacent to
roadway, regrading for swale
needed, block wall
potentially needed.
Pink route (Option 5, 1,000 FT)
10' trail installed adjacent to roadway,
regrading for swale needed, block wall
potentially needed.
Red (Option 1, 200 FT)
Excavate end of existing ped
tunnel, install wing walls on Blue Route (Option 2,
both sides, add lighting and 125 FT)
200 FT sidewalk ramp with
walls to access trail Route 10' trail
Sources
- revize: Hwy 6 Ped Underpass Options & Cost Estimate (I2LTBrGdVFAyz18LtZ4Y62hjbQF9wE.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: C Discussion and Review of Potential Funding Opportunities through the IDOT for Trail...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.