Text from the PDF text layer; check the PDF for anything that matters.February 24, 2021
Mayor and City Council.
The subdrains and outlets were installed at the depths specified on the plans. The ditch was
graded as specified on the electronic grading file but the subdrain outlets did not drain
properly. The problem was largely undetected until the final grading was complete and when
the IDOT made their final onsite inspection. Rathje was instructed to re-grade the ditch to
allow the subdrain outlets to drain to the extent feasible. Several truckloads of material were
removed from the ditch. The problem also occurred in several other places, but they are
requesting the change order for only the north ditch east of the school property where the
problem was most pronounced.
I support Rathje’s change order request as this makes for better drainage of the project and less
drainage issues in the future.
Thanks,
Benjamin A. Carhoff, P.E.
Hart-Frederick Consultants PC
510 State Street, PO Box 560
Tiffin, IA 52340-0560
P. 319-545-7215 F.319-545-7220
C.319-631-1081
[email protected]
Sources
- sharepoint (K-5 - Rathje Change Order Explanation - Roundabout.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.