staff report memo · E-4
Approval of State Revolving Fund (SRF) Reimbursement Request #7 - Water Treatment Facility Upgrade Project — E-4
Page 11 of 13
Text from the PDF text layer; check the PDF for anything that matters.Progress Estimate - Lump Sum Work Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: MSA Professional Services Engineer's Project No.: 13603016
Contractor: Tricon Construction Group Contractor's Project No.:
Project: Water Treatment Plant Upgrades - City of Tiffin
Contract:
Application No.: 12 Application Period: From 06/27/26 to 07/23/26 Application Date: 07/24/26
211 Process Piping Materials $111,340.84 - 66,925.48 66,925.48 60% 44,415.36
212 Process Piping Labor $85,502.50 2,137.56 2,137.56 2% 83,364.94
213 Valves Materials $83,000.00 - 29,765.00 29,765.00 36% 53,235.00
214 Valves Labor $30,614.26 - - 0% 30,614.26
215 Structure 30 - Clearwell - - -
216 Process Piping Materials $62,822.42 7,658.00 9,079.50 16,737.50 27% 46,084.92
217 Process Piping Labor $69,588.64 - - 0% 69,588.64
218 Valves Materials $42,830.00 - 10,554.50 10,554.50 25% 32,275.50
219 Valves Labor $26,450.68 - - 0% 26,450.68
220 Insulation $6,825.00 - - 0% 6,825.00
221 - - -
222 Pollution Control Equipment - - -
223 Vertical Turbine Pumps Materials $115,300.00 2,700.00 112,600.00 115,300.00 100% -
224 Vertical Turbine Pumps Labor $24,601.24 - - 0% 24,601.24
225 Slide Gates Materials $24,155.00 18,116.25 6,038.75 24,155.00 100% -
226 Slide Gates Labor $9,001.40 4,500.70 4,500.70 9,001.40 100% -
227 Clearwell Leak Testing $18,144.00 - - 0% 18,144.00
228 Lab Equipment $7,216.00 - 7,216.00 7,216.00 100% -
229 Filter Media Replacement Materials $49,780.00 49,780.00 49,780.00 100% -
230 Filter Media Replacement Labor $16,480.00 16,480.00 16,480.00 100% -
231 Forced Draft Aerator Materials $125,890.00 - 62,945.00 62,945.00 50% 62,945.00
232 Forced Draft Aerator Labor $14,995.00 749.75 749.75 5% 14,245.25
233 RO System Materials $1,408,500.00 281,700.00 281,700.00 20% 1,126,800.00
234 RO System Labor $203,600.00 - - 0% 203,600.00
235 Chem Sys Chlorine Fluoride Caustic $125,425.00 - 104,302.00 104,302.00 83% 21,123.00
236 Chem Systems Labor $41,582.00 4,158.20 4,158.20 10% 37,423.80
237 - - -
Original Contract Totals $ 12,182,553.00 $ 5,404,563.52 $1,235,779.52 $ 872,208.22 $ 7,512,551.26 62% $ 4,670,001.74
EJCDC® C-620 Contractor's Application for Payment
© National Society of Professional Engineers for EJCDC. All rights reserved. 00 62 76 - 9 of 11 G:\13\13603\13603021\Pay Apps\Pay App #11\13603021_Tiffin WTP Pay App #1 (IFA)
Sources
- revize: E-4 (7SfQWMK0QDpySdg9HDgdZ0D53C4YoP.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-4 Approval of State Revolving Fund (SRF) Reimbursement Request #7 - Water Treatment...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.