engineering report · L-2
City Engineer's Report [AMENDED] — L-2
Page 5 of 5
Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
August 28, 2026
PROJECT UPDATE
Upcoming Infrastructure
Description Next Steps/Schedule
Project
The current wastewater treatment facility (WWTF) has a chloride Final Compliance with NPDES
compliance schedule. There is not any wastewater treatment Permit required October 1, 2025.
equipment/processes designed to remove chloride so typically
source control is the only economical means of meeting MSA presented its findings on
Wastewater Treatment
compliance. The existing treatment facility is at about 50% November 1st, 2022. MSA has
Improvements
capacity. However, if the past growth rate continues an expansion prepared a proposed schedule
will be required in the next 5-7 years. for wastewater treatment, water
treatment and water supply
From design to construction the process typically takes 3-4 years. improvement projects.
Due to the City's continued growth and the new water treatment
plant, it was noted that Well #6 may need to be brought online
MSA will solicit quotes from
within the next 12 months. The only work recommended for the
Well 6 qualified well drilling
City is the well acidization and test pumping. The testing results will
contractors.
provide the information needed to properly size the pump,
watermain, electrical service, and other associated infrastructure.
North Park Road & Aster Drive MSA is preparing a PSA for review by the City to signalize this MSA is preparing a PSA for
Intersection Improvements intersection. review by the City.
PROJECT UPDATE
Page 5 of 5
Sources
- revize: L-2 (U1iMGaOlVmnDPmjQmBUo7TUFEsBVNx.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-2 City Engineer's Report [AMENDED]
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.