budget
WS - D - Opinion of Probabe Costs - PW Facility
Page 2 of 2
Text from the PDF text layer; check the PDF for anything that matters.Page 2 of 2 Project Management Spreadsheet Tiffin Public Services
www.MartinGardnerArch.com (Opinion of Probable Costs) 9/1/2021
GENERAL CONDITIONS
General Contracting Fees (General Requirements: 10%; O.H. and Profit is included in unit prices) 10% $196,646
Project Subtotal + General Conditions $2,163,103
CONSTRUCTION & DESIGN CONTINGENCIES
Estimating and Design Contingency (% of Project Subtotal) 10.0% $216,310
Construction Contingency (% of Project Subtotal) 8.0% $173,048
Subtotal Contingencies $389,359
Project Total $2,552,462
DESIGN FEES
MGA ARCHITECTRUAL, STRUCTURAL, MEPT $ 90,405
TERRACON BORINGS AND SOILS REPORT $ 3,250
SHIVE-HATTERY CIVIL ENGINEERING $ 23,310
SH - CA, staking testing $ 11,550
Subtotal Design Fees $128,515
Project Total $2,680,977
700 11th St., Ste. 200 11502 390th St.
Marion, IA 52302 Strawberry Point, IA 52076
P: (319) 377-7604 P: (563) 933-4712
F: (319) 377-1175 F: (563) 933-2052