Text read by the vision model; check the PDF for anything that matters.Date: September 13, 2021
To: Ben Carhoff
Project: Tiffin Original Town Urbanization Phase II
Re: COR #7
Rathje # 7187
Ben,
I am hereby submitting the following change order request for the lowering of the 4" raw water feed to maintain 5' of cover through the intersection of Main Street due to the new grades and the storm sewer conflict @ STA # 6+73, 5L. We will have to lay the main one day and the following day hook up the East end, put temporary blowoff on, flush the new line and then drain the line and connect the West end to the existing.
<table>
<tr>
<th>Item</th>
<th>Description</th>
<th>Qty</th>
<th>Unit</th>
<th>Unit Price</th>
<th>MU</th>
<th>Unit w/ MU</th>
<th>Total</th>
</tr>
<tr>
<td>4" Water Main</td>
<td></td>
<td>200.00</td>
<td>LF</td>
<td>$67.00</td>
<td>0.00%</td>
<td>$67.00</td>
<td>$13,400.00</td>
</tr>
<tr>
<td colspan="7">Total</td>
<td>$13,400.00</td>
</tr>
<tr>
<td>Additional Days Requested</td>
<td></td>
<td>2 EA</td>
<td></td>
<td></td>
<td></td>
<td>Total</td>
<td>2.0</td>
</tr>
</table>
Please call if you have any questions.
Respectfully,
Dan Scofield