Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # E-6
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: August 27, 2026
AGENDA ITEM: Approval of Change Order #18 – Boomerang Construction Group – North
Park Road Improvements Project
ACTION: Motion
Background
The City of Tiffin is completing the North Park Road Improvements project, identified as STP-
U-7662(615)--70-52, with Boomerang Corp. serving as the prime contractor. The original
awarded project amount is $5,458,891.91, and the currently authorized project amount is
$5,586,976.68.
Change Order No. 18 is classified as a non-substantial change order and was created on August
25, 2026. The purpose of the change order is to correct the treatment of a Modified Subbase
quantity that was included in Change Order No. 17.
The change order is necessary to correct a funding-category error associated with Change Order
No. 17. The Modified Subbase overrun quantity was originally included under Category 1
federal funding in Change Order No. 17 and was subsequently approved in the project
management system. Because Change Order No. 17 cannot be unapproved in the system, Change
Order No. 18 is being used to remove the quantity from the participating item and establish the
appropriate non-participating item.
Recommendation
Staff recommends that the City Council approve Change Order No. 18 with Boomerang Corp.
for the North Park Road Improvements project.
This change order is administrative/corrective in nature, results in no increase to the overall
project cost, has no impact on contract time, and corrects the funding categorization associated
with Modified Subbase work from Change Order No. 17.
ATTACHMENTS: Change Order
1
Sources
- revize: E-6 (hOhWEp62VdqTBpONdCx5jblp5RC4GA.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-6 Approval of Changer Order #18 - Boomerang Construction Group - North Park Road...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.