contract agreement · E-5
Approval of Pay Application #16 – Boomerang Construction Group – North Park Road Improvements Project — E-5
Page 20 of 21
Text from the PDF text layer; check the PDF for anything that matters.Summary
Current Approved Work: $342,708.08 Approved Work To Date: $4,699,146.63
Current Stockpile Advancement: $0.00 Stockpile Advancement To Date: $249,166.08
Current Stockpile Recovery: $34,676.97 Stockpile Recovery To Date: $220,371.75
Current Retainage: $0.00 Retainage To Date: $30,000.00
Current Retainage Released: $0.00 Retainage Released To Date: $0.00
Current Liquidated Damages: $0.00 Liquidated Damages To Date: $0.00
Current Adjustment: $0.00 Adjustments To Date: $0.00
Current Payment: $308,031.11 Payments To Date: $4,697,940.96
Previous Payment: $250,438.56 Previous Payments To Date: $4,389,909.85
Funding Details
52-7662-615-CAT-1 ROADWAY ITEMS: $342,708.08 52-7662-615-CAT-1 ROADWAY ITEMS To Date: $4,050,173.78
52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2: $0.00 52-7662-615-CAT-2 ROADWAY ITEMS - DIVISION 2 To Date: $648,972.85
New Fund 52-7662-615-CAT-3 NON-PARTICIPATINGackage: $0.00 New Fund 52-7662-615-CAT-3 NON-PARTICIPATINGackage To
$0.00
Date:
Current Payment: $342,708.08
Payments To Date: $4,699,146.63
Detailed Payment: 08/26/2026
52-7662-615 Page 19 of 19
Sources
- revize: E-5 (5ZAoHmSq1ZpKVPfpXZotcdzxVl7bGV.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-5 Approval of Pay Application #16 – Boomerang Construction Group – North Park Road...
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.