K-5 - Pay Estimate #1 - Vieth Construction - Trail Phase 6
Page 3 of 3
Text read by the vision model; check the PDF for anything that matters.<table>
<tr>
<th>ITEM NO.</th>
<th>CONTRACT ITEMS</th>
<th>UNIT</th>
<th>EST QTY</th>
<th>UNIT PRICE</th>
<th>CONTRACTOR'S BID PRICE</th>
<th colspan="2">Pay Period #1</th>
<th colspan="2">TOTAL TO DATE</th>
</tr>
<tr>
<th colspan="6">BID SCHEDULE</th>
<th>QTY</th>
<th>AMOUNT</th>
<th>QTY</th>
<th>AMOUNT</th>
</tr>
<tr>
<td>0010</td>
<td>Excavation, Class 10, Roadway and Borrow</td>
<td>CY</td>
<td>110.60</td>
<td>$75.00</td>
<td>$8,295.00</td>
<td>110.60</td>
<td>$8,295.00</td>
<td>110.60</td>
<td>$8,295.00</td>
</tr>
<tr>
<td>0020</td>
<td>Topsoil, Strip, Salvage, And Spread</td>
<td>CY</td>
<td>130.00</td>
<td>$30.00</td>
<td>$3,900.00</td>
<td>130.00</td>
<td>$3,900.00</td>
<td>130.00</td>
<td>$3,900.00</td>
</tr>
<tr>
<td>0030</td>
<td>Subgrade Stabilization Material, PC or Flyash</td>
<td>SY</td>
<td>754.00</td>
<td>$16.00</td>
<td>$12,064.00</td>
<td>584.90</td>
<td>$9,358.40</td>
<td>584.90</td>
<td>$9,358.40</td>
</tr>
<tr>
<td>0040</td>
<td>Shoulder Finishing, Earth</td>
<td>STA</td>
<td>10.30</td>
<td>$225.00</td>
<td>$2,317.50</td>
<td>10.30</td>
<td>$2,317.50</td>
<td>10.30</td>
<td>$2,317.50</td>
</tr>
<tr>
<td>0050</td>
<td>Recreational Trail, PCC 6 in.</td>
<td>SY</td>
<td>562.50</td>
<td>$45.00</td>
<td>$25,312.50</td>
<td>521.11</td>
<td>$23,449.95</td>
<td>521.11</td>
<td>$23,449.95</td>
</tr>
<tr>
<td>0060</td>
<td>Special Compaction of Subgrade for Recreational Trail</td>
<td>STA</td>
<td>5.15</td>
<td>$400.00</td>
<td>$2,060.00</td>
<td>5.15</td>
<td>$2,060.00</td>
<td>5.15</td>
<td>$2,060.00</td>
</tr>
<tr>
<td>0070</td>
<td>Detectable Warning</td>
<td>SF</td>
<td>60.00</td>
<td>$44.00</td>
<td>$2,640.00</td>
<td>60.00</td>
<td>$2,640.00</td>
<td>60.00</td>
<td>$2,640.00</td>
</tr>
<tr>
<td>0080</td>
<td>Entrance Bollard</td>
<td>EACH</td>
<td>1.00</td>
<td>$1,250.00</td>
<td>$1,250.00</td>
<td>1.00</td>
<td>$1,250.00</td>
<td>1.00</td>
<td>$1,250.00</td>
</tr>
<tr>
<td>0090</td>
<td>Wood Post, Type A Sign 4"x4"</td>
<td>LF</td>
<td>112.00</td>
<td>$44.00</td>
<td>$4,928.00</td>
<td>112.00</td>
<td>$4,928.00</td>
<td>112.00</td>
<td>$4,928.00</td>
</tr>
<tr>
<td>0100</td>
<td>Type A sign, sheet aluminum</td>
<td>SP</td>
<td>18.00</td>
<td>$33.00</td>
<td>$594.00</td>
<td>19.25</td>
<td>$635.25</td>
<td>19.25</td>
<td>$635.25</td>
</tr>
<tr>
<td>0110</td>
<td>Painted Pavement Markings, Waterborne or Solvent Based</td>
<td>STA</td>
<td>5.39</td>
<td>$200.00</td>
<td>$1,078.00</td>
<td>5.54</td>
<td>$1,662.00</td>
<td>5.54</td>
<td>$1,662.00</td>
</tr>
<tr>
<td>0120</td>
<td>Painted Symbols and Legends, Waterborne or Solvent Based</td>
<td>BACH</td>
<td>2.00</td>
<td>$150.00</td>
<td>$300.00</td>
<td>2.00</td>
<td>$300.00</td>
<td>2.00</td>
<td>$300.00</td>
</tr>
<tr>
<td>0130</td>
<td>Traffic Control</td>
<td>LS</td>
<td>1.00</td>
<td>$4,500.00</td>
<td>$4,500.00</td>
<td>1.00</td>
<td>$4,500.00</td>
<td>1.00</td>
<td>$4,500.00</td>
</tr>
<tr>
<td>0140</td>
<td>Mobilization</td>
<td>LS</td>
<td>1.00</td>
<td>$13,500.00</td>
<td>$13,500.00</td>
<td>1.00</td>
<td>$13,500.00</td>
<td>1.00</td>
<td>$13,500.00</td>
</tr>
<tr>
<td>0150</td>
<td>Railroad Protective Liability Insurance, IAIS</td>
<td>LS</td>
<td>1.00</td>
<td>$2,000.00</td>
<td>$2,000.00</td>
<td>1.00</td>
<td>$2,000.00</td>
<td>1.00</td>
<td>$2,000.00</td>
</tr>
<tr>
<td>0160</td>
<td>Treated Posts 6'x6"x6'</td>
<td>LF</td>
<td>12.00</td>
<td>$11.00</td>
<td>$132.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>0170</td>
<td>Mulching</td>
<td>ACRE</td>
<td>0.30</td>
<td>$2,175.00</td>
<td>$652.50</td>
<td>0.30</td>
<td>$652.50</td>
<td>0.30</td>
<td>$652.50</td>
</tr>
<tr>
<td>0180</td>
<td>Seeding and Fertilize (Urban)</td>
<td>ACRE</td>
<td>0.30</td>
<td>$2,175.00</td>
<td>$652.50</td>
<td>0.30</td>
<td>$652.50</td>
<td>0.30</td>
<td>$652.50</td>
</tr>
<tr>
<td>0190</td>
<td>Silt Fence</td>
<td>LF</td>
<td>410.00</td>
<td>$2.25</td>
<td>$922.50</td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>0200</td>
<td>Removal of Silt Fence</td>
<td>LF</td>
<td>410.00</td>
<td>$0.55</td>
<td>$225.50</td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>0210</td>
<td>Maintenance of Silt Fence</td>
<td>LF</td>
<td>410.00</td>
<td>$0.55</td>
<td>$225.50</td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>0220</td>
<td>Mobilizations, Erosion Control</td>
<td>EACH</td>
<td>3.00</td>
<td>$500.00</td>
<td>$1,500.00</td>
<td>1.00</td>
<td>$500.00</td>
<td>1.00</td>
<td>$500.00</td>
</tr>
<tr>
<th colspan="6">TOTAL OF THE BASE BID (Total of Items 1-X):</th>
<th>$89,588.50</th>
<th>$82,601.10</th>
<th>$82,601.10</th>
</tr>
<tr>
<td>CO1</td>
<td>HMA at Railroad Crossing (includes materials & labor)</td>
<td>LS</td>
<td>1.00</td>
<td>$2,138.00</td>
<td>$2,138.00</td>
<td>1.00</td>
<td>$2,138.00</td>
<td>1.00</td>
<td>$2,138.00</td>
</tr>
<tr>
<td>CO2</td>
<td></td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$0.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>CO3</td>
<td></td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$0.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>CO4</td>
<td></td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$0.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>CO5</td>
<td></td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$0.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>CO6</td>
<td></td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$0.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>CO7</td>
<td></td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$0.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<th colspan="6">CHANGE ORDER SUB-TOTAL</th>
<th>$2,138.00</th>
<th>$2,138.00</th>
</tr>
<tr>
<th colspan="6">AMOUNT EARNED TOTAL</th>
<th>$84,739.10</th>
<th>$84,739.10</th>
</tr>
<tr>
<td>9998</td>
<td>Materials Stored on-site</td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$0.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>9999</td>
<td>Materials Installed on-site (Deduct)</td>
<td></td>
<td></td>
<td>$0.00</td>
<td>$0.00</td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<th colspan="6">MATERIALS SUB-TOTAL</th>
<th>$0.00</th>
<th>$0.00</th>
</tr>
<tr>
<th colspan="6">TOTAL</th>
<th>$84,739.10</th>
<th>$84,739.10</th>
</tr>
</table>