Text read by the vision model; check the PDF for anything that matters.Date: October 8, 2021
To: Ben Carhoff
Project: Tiffin Original Town Urbanization Phase II
Re: COR #8
Rathje # 7187
Ben,
I am hereby submitting the following change order request for the exploration of the sanitary sewer service @ 211 W Second Street. We got a call from the city to dig up a sanitary sewer service that we had replaced recently due to a Sewer back up at that property and found the problem was not ours it was closer to the house. Brett told Dave to bill for our time.
<table>
<tr>
<th>Item</th>
<th>Description</th>
<th>Qty</th>
<th>Unit</th>
<th>Unit Price</th>
<th>MU</th>
<th>Unit w/ MU</th>
<th>Total</th>
</tr>
<tr>
<td>Sanitary Service Exploration</td>
<td></td>
<td>1.00</td>
<td>EA</td>
<td>$2,500.00</td>
<td>0.00%</td>
<td>$2,500.00</td>
<td>$2,500.00</td>
</tr>
<tr>
<td colspan="6">Total</td>
<td colspan="2">$2,500.00</td>
</tr>
<tr>
<td>Additional Days Requested</td>
<td></td>
<td>0</td>
<td>EA</td>
<td></td>
<td></td>
<td>Total</td>
<td>0.0</td>
</tr>
</table>
Please call if you have any questions.
Respectfully,
Dan Scofield