Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # E-5
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: August 27, 2026
AGENDA ITEM: Approval of Pay Application #16 – Boomerang Construction Group – North
Park Road Improvements Project
ACTION: Motion
Background
The City of Tiffin is currently completing improvements associated with the North Park Road
project, identified as STP-U-7662(615)--70-52. The project was let on December 17, 2024, with
Boomerang Corp. serving as the prime contractor. The awarded project amount is $5,458,891.91,
with an authorized amount of $5,586,976.68.
Pay Application No. 16 covers the work performed during the period of July 26, 2026, through
August 22, 2026. The payment application is currently identified as pending and was prepared
through the City's project payment system.
For Pay Application No. 16, Boomerang Corp. has submitted $342,708.08 in approved work for
the current billing period. The application also reflects a $34,676.97 stockpile recovery, resulting
in a current payment of $308,031.11. No retainage, liquidated damages, or other adjustments are
being applied to the current payment.
Work completed to date includes significant roadway, pavement, drainage, utility, and pedestrian
improvements. The detailed pay application identifies completed work including concrete
pavement, storm sewer infrastructure, culverts, water main installation, fire hydrant assemblies,
recreational trail improvements, erosion control, traffic control, and other roadway-related
improvements.
During the current pay period, notable work included approximately 6,139.54 square yards of
Portland cement concrete pavement, generating $331,535.16 in current-period payment for that
item. Additional current-period work included modified subbase, pavement removal, driveway
removal, silt fence, sediment control, and erosion-control mobilization.
The payment documentation also indicates that the project remains within its authorized
schedule. The original time limit was 200 working days, with an authorized deadline of 210
working days. As of the current payment application, 146.5 working days have been completed
with 63.5 working days remaining. The report shows no liquidated damages assessed to date.
Recommendation
Staff recommends that the City Council approve Pay Application No. 16 from Boomerang Corp.
in the amount of $308,031.11 for the North Park Road Improvements project.
ATTACHMENTS: Pay Application
1
Sources
- revize: E-5 (5ZAoHmSq1ZpKVPfpXZotcdzxVl7bGV.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-5 Approval of Pay Application #16 – Boomerang Construction Group – North Park Road...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.