other · M-8
M-8 - Original Town Schedule - Winter Shutdown
Page 1 of 1
Text from the PDF text layer; check the PDF for anything that matters. October 15, 2021
Tiffin Original Town Urbanization ‐ Phase 2
Tentative Construction Schedule
October November December
Week of 10/22 Week of 10/29 Week of 11/5 Week of 11/12 Week of 11/19 Week of 11/26 Week of 12/3 Week of 12/10 Week of 12/17 Week of 12/24
Complete Areas Currently Under Construction
Backfill Curb and Gutter
Sidewalks/Drives
Topsoil
Complete 2nd Avenue and Main Street Intersection
Paving
Brick Paver/ACC Setting Bed
Backfill Curb and Gutter
Complete Main Street
Subgrade Preparation
Subbase Rock
Paving
Backfill Curb and Gutter
Sidewalks/Drives
Topsoil
***Schedule is subject to Franchise Utilties completing their utility relocations
Sources
- sharepoint (M-8 - Original Town Schedule - Winter Shutdown.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.