Text read by the vision model; check the PDF for anything that matters.Date: November 19, 2021
To: Ben Carhoff
Project: Tiffin Original Town Urbanization Phase II
Re: COR #13
Rathje # 7187
Ben,
I am hereby submitting the following change order request for the installation of ACC Millings at the intersection of 2nd Avenue and Main Street, and for various utility crossings during winter months. Tonnage will be paid on load tickets. Quantity indicated below will vary.
<table>
<tr>
<th>Item</th>
<th>Description</th>
<th>Qty</th>
<th>Unit</th>
<th>Unit Price</th>
<th>MU</th>
<th>Unit w/ MU</th>
<th>Total</th>
</tr>
<tr>
<td>ACC Millings</td>
<td></td>
<td>83.33</td>
<td>Ton</td>
<td>$30.00</td>
<td>0.00%</td>
<td>$30.00</td>
<td>$2,499.90</td>
</tr>
<tr>
<td colspan="6">Total</td>
<td>$2,499.90</td>
</tr>
<tr>
<td>Additional Days Requested</td>
<td></td>
<td>0</td>
<td>EA</td>
<td></td>
<td></td>
<td>Total</td>
<td>0.0</td>
</tr>
</table>
Please call if you have any questions.
Respectfully,
Dan Scofield