<th colspan="2">Progress Estimate - Lump Sum Work</th>
<th colspan="2">Contractor's Application for Payment</th>
</tr>
<tr>
<td>Owner:</td>
<td>City of Tiffin</td>
<td>Owner's Project No.:</td>
<td></td>
</tr>
<tr>
<td>Engineer:</td>
<td>MSA Professional Services</td>
<td>Engineer's Project No.:</td>
<td>13603016</td>
</tr>
<tr>
<td>Contractor:</td>
<td>Tricon Construction Group</td>
<td>Contractor's Project No.:</td>
<td></td>
</tr>
<tr>
<td>Project:</td>
<td>Water Treatment Plant Upgrades - City of Tiffin</td>
<td colspan="2"></td>
</tr>
<tr>
<td>Contract:</td>
<td colspan="3"></td>
</tr>
<tr>
<td>Application No.: 13</td>
<td>Application Period: From 08/22/26 to 09/24/26</td>
<td>Application Date: 09/25/26</td>
<td></td>
</tr>
<tr>
<th colspan="5">Change Orders</th>
</tr>
<tr>
<td>238</td>
<td>Change Order #1</td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>239</td>
<td>Electrical Controls Changes</td>
<td>$12,420.34</td>
<td>12,420.34</td>
<td>12,420.34 100%</td>
</tr>
<tr>
<td>240</td>
<td></td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>241</td>
<td>Change Order #2</td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>242</td>
<td>COR #003R2-Water Service Addition</td>
<td>3,545.10</td>
<td>3,018.07</td>
<td>3,018.07 85% 527.03</td>
</tr>
<tr>
<td>243</td>
<td>COR-004+-Xfmr Pad relocate & bollards</td>
<td>1,804.21</td>
<td>-</td>
<td>- 0% 1,804.21</td>
</tr>
<tr>
<td>244</td>
<td>COR -006 - Chem Containment Curbs</td>
<td>1,022.01</td>
<td>1,022.01</td>
<td>1,022.01 100%</td>
</tr>
<tr>
<td>245</td>
<td>COR -007 - Bldg 10 Load Brg Wall Chngs</td>
<td>2,556.62</td>
<td>2,556.62</td>
<td>2,556.62 100%</td>
</tr>
<tr>
<td>246</td>
<td>COR-008R-12" Valve Add,6" Valve Deducts</td>
<td>(1,619.74)</td>
<td>(1,619.74)</td>
<td>(1,619.74) 100%</td>
</tr>
<tr>
<td>247</td>
<td>COR-010-MCC Rm Intake Duct Addition</td>
<td>3,402.31</td>
<td>-</td>
<td>- 0% 3,402.31</td>
</tr>
<tr>
<td>248</td>
<td>COR-012-Low Lift Pump Efficiency Credit</td>
<td>(2,890.94)</td>
<td>(2,890.94)</td>
<td>(2,890.94) 100%</td>
</tr>
<tr>
<td>249</td>
<td></td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>250</td>
<td></td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>251</td>
<td></td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>252</td>
<td></td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>253</td>
<td></td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>254</td>
<td></td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>255</td>
<td></td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>256</td>
<td></td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td>257</td>
<td></td>
<td>-</td>
<td>-</td>
<td>-</td>
</tr>
<tr>
<td colspan="2">Change Order Totals</td>
<td>$20,239.91</td>
<td>$2,086.02</td>
<td>$12,420.34 $14,506.36 72% $5,733.55</td>
</tr>
<tr>
<th colspan="5">Original Contract and Change Orders</th>
</tr>
<tr>
<td>Project Totals</td>
<td>$12,202,792.91</td>
<td>$8,552,711.10</td>
<td>$1,304,981.24</td>
<td>$352,376.61 $10,210,068.95 84% $1,992,723.96</td>
</tr>
</table>