Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER REQUEST
DATE: 8/14/2025
CONTRACT #: 0
CHANGE ORDER REQUEST NO.: 7
PROJECT: Tiffin Phase 3 Reconstruction Project
CONTRACTOR: Rathje Construction
CONTRACTOR PROJECT MANAGER: Dan Scofield
CITY OF TIFFIN CONSTRUCTION PROJECT MANAGER: Ben Carhoff
DESCRIPTION OF REQUEST:
1. It was discovered after subgrade was established in the intersection of Third & Grant that the watermain would only have roughly 3.5' of frost protection after the paving was complete. It was requested to install 6" of Rigid Styrofoam board over top of the watermain for added frost protection. Price below includes, exploratory digging, class 10 excavation, equipment, labor and materials to install the Rigid Styrofoam. Total measurement was 180' x 4' and displaced 13.7 CY of material. We actually dug down 12-18" so we could get some material on top of the Styrofoam to ensure it did not destroyed with truck traffic.
SUDAS SPECIFICATION SECTION TO SUPPORT REQUEST, DIVISION 1:
JUSTIFICATION FOR THE REQUEST, WORKING DIVISION:
<table>
<tr>
<th>Line No.</th>
<th>Spec. #</th>
<th>Item No.</th>
<th>Item Description</th>
<th>Quantity</th>
<th>Unit</th>
<th>Unit Price</th>
<th>Mark up</th>
<th>Unit Price w/ Markup</th>
<th>Working Days Requested</th>
<th>Proposed Increase (Decrease) In Contract Price</th>
</tr>
<tr>
<td>1</td>
<td></td>
<td>8018</td>
<td>Rigid Foam Board Insulation 6"</td>
<td>720.00</td>
<td>SF</td>
<td>$17.00</td>
<td>0.00%</td>
<td>$17.00</td>
<td>1</td>
<td>$12,240.00</td>
</tr>
</table>
Net Increase (Decrease): 1 $12,240.00
SUPPORT DOCUMENTS INCLUDED:
CONTRACT TIME IMPACT: (N/A)
REVISED SCHEDULE PROVIDED? YES or NO
STANDARD SUDAS BID ITEMS MUST BE USED IF POSSIBLE; OTHERWISE PROVIDE COST BREAKDOWN:
INVOICES (REQUIRED):
MATERIAL SUBMITTALS (REQUIRED):
ADDITIONAL SUPPORT DOCUMENTS INCLUDED:
This document does not change the Contract Price or Contract Time but is evidence that the parties expect that the subject changes will be incorporated into a subsequent Contract Change Order following negotiation by the parties as to effect, if any, upon Contract Price or Contract Time. Work shall not be deemed acknowledged per Division 1, General Provisions and Covenants until all signatures are received. Payment related to this document will only be made after execution of Contract Change Order through City Council.