Text from the PDF text layer; check the PDF for anything that matters.Progress Estimate - Lump Sum Work Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: MSA Professional Services Engineer's Project No.: 13603030
Contractor: Neumiller Electric, Inc Contractor's Project No.: 26-084-U
Project: Roberts Ferry Rd & Village Dr Traffic Signal Improvements
Contract: Traffic Signal Improvements
Application No.: 1 Application Period: From 06/02/26 to 09/20/26 Application Date: 09/25/26
Change Orders
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
Change Order Totals $ - $ - $ - $ - $ - $ -
Original Contract and Change Orders
Project Totals $ 277,000.00 $ - $ 65,780.29 $ 97,380.00 $ 163,160.29 59% $ 113,839.71
EJCDC® C-620 Contractor's Application for Payment
© National Society of Professional Engineers for EJCDC. All rights reserved. 00 62 76 - 5 of 6 G:\13\13603\13603030\Construction\14 Pay Applications\Pay Application 01\13603030 - Roberts Ferry & Village Drive Signal - Pay Application #01.xlsx