To: Ben Carhoff
Project: Tiffin Original Town Urbanization Phase II
Re: COR #14 R
Rathje # 7187
Ben,
I am hereby submitting the following change order request for the regrading from the right of way to the front of the houses to obtain positive drainage at 230 and 240 Summerhayes Drive.
<table>
<tr>
<th>Item</th>
<th>Description</th>
<th>Qty</th>
<th>Unit</th>
<th>Unit Price</th>
<th>MU</th>
<th>Unit w/ MU</th>
<th>Total</th>
</tr>
<tr>
<td>Extra Grading</td>
<td></td>
<td>297.40</td>
<td>SY</td>
<td>$15.00</td>
<td>0.00%</td>
<td>$15.00</td>
<td>$4,461.00</td>
</tr>
<tr>
<td colspan="7">Total</td>
<td>$4,461.00</td>
</tr>
<tr>
<td>Additional Days Requested</td>
<td></td>
<td>0 EA</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td>0.0</td>
</tr>
<tr>
<td colspan="7">Total</td>
<td>0.0</td>
</tr>
</table>
Please call if you have any questions.
Respectfully,
Dan Scofield