contract agreement · K-2

K-2 - Change Order 13 - Rathje Construction - Original Town Phase Two

Open the PDF Searchable (OCR) PDF

Page 2 of 2

Text read by the vision model; check the PDF for anything that matters.
Date: January 5, 2022 To: Ben Carhoff Project: Tiffin Original Town Urbanization Phase II Re: COR #14 R Rathje # 7187 Ben, I am hereby submitting the following change order request for the regrading from the right of way to the front of the houses to obtain positive drainage at 230 and 240 Summerhayes Drive. <table> <tr> <th>Item</th> <th>Description</th> <th>Qty</th> <th>Unit</th> <th>Unit Price</th> <th>MU</th> <th>Unit w/ MU</th> <th>Total</th> </tr> <tr> <td>Extra Grading</td> <td></td> <td>297.40</td> <td>SY</td> <td>$15.00</td> <td>0.00%</td> <td>$15.00</td> <td>$4,461.00</td> </tr> <tr> <td colspan="7">Total</td> <td>$4,461.00</td> </tr> <tr> <td>Additional Days Requested</td> <td></td> <td>0 EA</td> <td></td> <td></td> <td></td> <td></td> <td>0.0</td> </tr> <tr> <td colspan="7">Total</td> <td>0.0</td> </tr> </table> Please call if you have any questions. Respectfully, Dan Scofield

Sources

  • sharepoint (K-2 - Change Order 13 - Rathje Construction - Original Town Phase Two.pdf) — where it was found ↗ first seen Oct 12, 2026

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.