Text from the PDF text layer; check the PDF for anything that matters. ENGINEER'S OPINION OF PROBABLE COSTS
10' Pedestrian Trail Options & Pedestrian Underpass, US 6
Tall Grass Avenue to Roberts Ferry Road
Tiffin, IA
DATE: 9/16/2026 Estimate Year 2026
MSA PROJECT #: 13603026 Construction Year 2028
Underpass Work West Connection North Connection East Connection Project Total
Excavation, wing walls, 1500' of proposed Trail 1000' of proposed Trail
700' of proposed Trail from
lighting, proposed Trail from Culvert, west, to from Culvert, east, to
Culvert, north, to Redbird Run
connections Deerview Avenue Roberts Ferry Road
ITEM
DESCRIPTION UNIT UNIT PRICE QUANTITY COST QUANTITY COST QUANTITY COST QUANTITY COST QUANTITY TOTAL PRICE
NO.
1 Clearing & Grubbing LS $ 10,000.00 - $ - 0.40 $ 4,000 0.30 $ 3,000 0.30 $ 3,000 1 $ 10,000
2 Fill, Contractor Furnished CY $ 22.00 - $ - 1,182 $ 26,100 - $ - - $ - 1,182 $ 26,100
3 Excavation CY $ 10.00 2,900 $ 29,000 717 $ 7,200 246 $ 2,500 1,025 $ 10,300 4,888 $ 49,000
4 PCC Overlay inside underpass (ADA Compliance) SY $ 63.00 210 $ 13,300 - $ - - $ - - $ - 210 $ 13,300
5 PCC Endwalls with Pipe Railing at top EA $ 52,000.00 2 $ 104,000 - $ - - $ - - $ - 2 $ 104,000
6 Storm Sewer for Pedestrian Underpass (based on Oct. 2008 design) LS $ 32,500.00 1 $ 32,500 - $ - - $ - - $ - 1 $ 32,500
7 Drainage (Minor Storm Piping) LF $ 150.00 30 $ 4,500 200 $ 30,000 45 $ 6,800 60 $ 9,000 335 $ 50,300
8 Guardrail LF $ 30.00 200 $ 6,000 - $ - - $ - - $ - 200 $ 6,000
9 Anti-Graffiti Coating LS $ 12,500.00 1 $ 12,500 - $ - - $ - - $ - 1 $ 12,500
10 Underpass Lighting System LS $ 37,000.00 1 $ 37,000 - $ - $ - - $ - 1 $ 37,000
11 Pedestrian Hand Rail LF $ 210.00 475 $ 99,800 - $ - - $ - - $ - 475 $ 99,800
12 Modular Block Retaining Wall (Assume a ~3'-4' wall height average) SF $ 70.00 - $ - 6,000 $ 420,000 - $ - 5,000 $ 350,000 11,000 $ 770,000
13 Poured Concrete Retaining Wall (Assume an 8' 6" max height) CY $ 1,250.00 49 $ 61,250 - $ - - $ - - 49 $ 61,250
14 PCC Trail, 10' Wide, 6" Thickness SY $ 60.00 361 $ 21,660 1,667 $ 100,000 778 $ 46,700 1,111 $ 66,700 3,917 $ 235,060
15 PCC Trail Aggregate Base & Subbgrade Prep, 4" Thickness SY $ 10.00 167 $ 1,670 2,000 $ 20,000 933 $ 9,400 1,333 $ 13,400 4,434 $ 44,470
16 Construction Survey (1%) LS 1% $ 5,000 $ 7,000 $ 1,000 $ 5,000 1 $ 18,000
17 Traffic Control (3%) LS 2% $ 9,000 $ 13,000 $ 2,000 $ 10,000 1 $ 34,000
18 Mobilization (8%) LS 8% $ 35,000 $ 51,000 $ 6,000 $ 38,000 1 $ 130,000
ESTIMATED CONSTRUCTION SUBTOTAL $ 472,180 $ 678,300 $ 77,400 $ 505,400 $ 1,733,280
Contingency 20% $ 94,500 $ 135,700 $ 15,500 $ 101,100 $ 346,800
Inflation 5% per year $ 58,100 $ 83,500 $ 9,600 $ 62,200 $ 213,400
ESTIMATED CONSTRUCTION COST (2028) $ 624,780 $ 897,500 $ 102,500 $ 668,700 $ 2,293,480
Estimated Grant/Loan Administration $ - $ - $ - $ - $ -
Estimated Legal Fees $ - $ - $ - $ - $ -
Estimated Property Acquisition $ - $ - $ - $ - $ -
Estimated Design Engineering 10% $ 62,500 $ 89,800 $ 10,300 $ 66,900 $ 229,500
Estimated Construction Engineering 10% $ 62,500 $ 89,800 $ 10,300 $ 66,900 $ 229,500
TOTAL ESTIMATED PROJECT COST: $ 750,000 $ 1,078,000 $ 124,000 $ 803,000 $ 2,753,000
Disclaimers & Assumptions
1 This opinion of probable cost is approximate. Actual construction bids may vary significantly from this opinion due to timing of bids, constructual schedule restraints, labor rate increases, material increases, or other factors beyond the control of the engineer.
2 Unit prices are based on bids received from similar projects and bid prices from within the past two years from statewide Iowa DOT lettings.
3 Easements are estimations only. Compensation will be adjusted as needed during negotiations.
4 No street lighting or private utility relocation costs included.
5 Existing Culvert is 12' Wide, 8' Tall, 75' long
6 Proposed End Section and Headawall will be 41' long on each side
7 Total length is 157'
8 Rough length of wingwall is 30.5' plus a minimum 4' end section. For space reasons, it is assumed that the wingwall may tie into the poured ramp retaining wall at an approx. height of 5'. This location is west of the underpass and south of the first ramp.
G:\13\13603\13603028\_Pedestrian Underpass Hwy 6\TA Set-Aside Grant Application\backup\Attachment E - Itemized Breakdown of Cost Completed By:
Sources
- revize: H-1 (qqh90ssRBjM0YMSB9978GDhkmHl9AG.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: H-1 Resolution No. 2026-047 A Resolution Approving the Iowa Statewide Transportation...
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.