contract agreement · K-4
K-4 - Pay Estimate 1 - Well 5 Pump, Controls, Watermain - Boomerang
Page 2 of 2
Text from the PDF text layer; check the PDF for anything that matters. SUMMARY
Total Approved Total Completed
Contract Price $ 779,550.00 $ 172,558.50
Approved Change Order (list each)
Revised Contract Price $ 779,550.00 $ 172,558.50
Stored $ 48,842.70
Total Earned $ 221,401.20
Retainage (5%) $ 11,070.06
Total Earned Less Retainage $ 210,331.14
Total Previously Approved (list each)
Total Previously Approved $ -
Percent Complete 22% Amount Due This Request $ 210,331.14
The amount $210,331.14 is recommended for approval for payment in accordance with the terms of the contract.
Prepared By: Recommended By: Approved By:
Boomerang Corp. Veenstra & Kimm, Inc. Tiffin, Iowa
Signature: Keegan Parizek Signature: Signature:
Name: Keegan Parizek Name: Dave Schechinger Name:
Title: Project Manager Title: Engineer Title:
Date: February 1, 2023 Date: February 1, 2023 Date:
V&K Job No. 5093/1 2 of 2