M-6 - Engineer Report
Page 1 of 3
Text from the PDF text layer; check the PDF for anything that matters. PROJECT UPDATE A Review of MSA Projects in Your Community
City of Tiffin, IA
CLIENT LIAISONS:
Kevin Bailey, PE / Jake Huck, P.E.
Office: 319.364.4773
Cell(s): 319.855.8392/ 563.542.6571
[email protected] / [email protected]
DATE:
March 3, 2023
ON-GOING PROJECTS
North Park Road Improvements
The MSA design team continues working on preliminary design efforts required for the Concept Statement
submittal. Kevin Bailey and other engineers on the project will meet with City staff to discuss the preliminary
design and plans on Thursday, March 9th at City Hall. The Concept Statement will be submitted to the IowaDOT
on or before March 21, 2023.
Highway 6 Concept and Cost Estimate
MSA submitted conceptual plans and typical section to the Iowa DOT for review on July 25, 2022. The IowaDOT
provided comments on December 20, 2022. MSA is revising the typical sections for pavement depths based
on the IowaDOT comments. The concept, typical sections and cost estimate will be finalized in March and
reviewed with the City.
Comprehensive Water System Evaluation
MSA has the water model completed. We are currently in the process of setting up a meeting with Brent and
Doug to discuss.
MSA has contacted Harn RO Systems and Wigen Water Technologies for proposals to complete the pilot testing
for the Reverse Osmosis (RO) System. Harn is the only manufacturer that provided pricing. The piloting
proposal was about $70,000. Including the City’s responsibilities, the total estimated cost for the piloting would
be about $90,000. These piloting costs are reimbursable through the SRF Planning and Design loan if the City
want to pursue for financing.
A 90-day pilot is required if the iron filters would be removed from the water plant. If the iron filters remain,
a pilot would not be required by the DNR. If pilot testing is desired, we will move quickly to have that scheduled
for this spring.
Trail Connection between Roundabout and Parking Lot
Three conceptual layouts have been prepared and will be discussed with City staff on March 9th. Once a
conceptual alignment has been selected, the design and plans will be completed.
PROJECT UPDATE
Page 1 of 3