Text from the PDF text layer; check the PDF for anything that matters. PAY ESTIMATE NO. 4
May 1, 2023 WELL 5 PUMP, CONTROLS & WATER MAIN
TIFFIN, IOWA
Boomerang Corp. Contract Amount $779,550.00
13225 Circle Drive, Suite A Contract Date August 2, 2022
Anamosa, IA 52205 Pay Period March 25, 2023 - April 30, 2023
BID ITEMS
Estimated Quantity
Description Unit Quantity Unit Price Extended Price Completed Value Completed
1.1 Mobilization LS xxxxx xxxxx $ 89,000.00 100% $ 89,000.00
1.2 Traffic Control LS xxxxx xxxxx $ 1,500.00 100% $ 1,500.00
1.3 Construction Staking LS xxxxx xxxxx $ 2,500.00 100% $ 2,500.00
1.4 Grading LS xxxxx xxxxx $ 15,000.00 90% $ 13,500.00
1.5 Seeding LS xxxxx xxxxx $ 1,000.00 60% $ 600.00
1.6 Erosion Control LS xxxxx xxxxx $ 1,000.00 90% $ 900.00
1.7 Erosion Control Blankets SY 500 $ 3.00 $ 1,500.00 0 $ -
1.8 Silt Fence LF 4,000 $ 0.50 $ 2,000.00 1,467 $ 733.50
1.9 Stabilizing Material CY 50 $ 50.00 $ 2,500.00 $ -
1.10 Water Main in Place $ -
1.10.1 8" PVC LF 1,960 $ 70.00 $ 137,200.00 1,960 $ 137,200.00
1.11 Water Main Augered in Place $ -
1.11.1 8" RJ DIP LF 100 $ 900.00 $ 90,000.00 100 $ 90,000.00
1.12 Hydrant Assembly Ea. 4 $ 7,000.00 $ 28,000.00 4 $ 28,000.00
1.13 Gate Valves with Box $ -
1.13.1 8" Ea. 3 $ 3,000.00 $ 9,000.00 3 $ 9,000.00
1.14 Connections to Existing Water Syste Ea. 2 $ 3,000.00 $ 6,000.00 2 $ 6,000.00
1.15 Well 5 Submersible Pump Ea. 1 $ 25,000.00 $ 25,000.00 1 $ 25,000.00
1.16 Pitless Unit Ea. 1 $ 20,000.00 $ 20,000.00 1 $ 20,000.00
1.17 Discharge Pipe LF 270 $ 150.00 $ 40,500.00 270 $ 40,500.00
1.18 Meter Manhole LS xxxxx xxxxx $ 45,000.00 100% $ 45,000.00
1.19 Surface Replacement
1.19.1 6" PCC Trail SY 40 $ 120.00 $ 4,800.00 45 $ 5,400.00
1.19.2 Granular Surfacing Tons 350 $ 33.00 $ 11,550.00 $ -
1.20 Rip-rap Tons 40 $ 75.00 $ 3,000.00 $ -
1.21 Field Drain Lines LF 100 $ 35.00 $ 3,500.00 100 $ 3,500.00
1.22 Clearing & Grubbing LS xxxxx xxxxx $ 20,000.00 100% $ 20,000.00
1.23 Controls Integration LS xxxxx xxxxx $ 130,000.00 70% $ 91,000.00
1.24 Controls & Electrical LS xxxxx xxxxx $ 90,000.00 70% $ 63,000.00
Contract Price: $ 779,550.00 $ 692,333.50
MATERIALS STORED SUMMARY
Description # of Units Unit Price Extended Cost
1.15 Well 5 Submersible Pump $ 12,881.51 $ -
1.16 Pitless Unit $ 12,587.14 $ -
1.17 Discharge Pipe $ 20,242.05 $ -
1.24 Controls & Electric $ 3,132.00 $ -
1.24 Controls & Electric $ 1,530.00 $ -
Total $ -
V&K Job No. 5093/1 1 of 2