Text read by the vision model; check the PDF for anything that matters.RESOLUTION NO. 2023-045
A RESOLUTION FOR THE COMPLETION AND FINAL ACCEPTANCE OF THE ORIGINAL TOWN URBANIZATION PROJECT – PHASE TWO, TIFFIN, IOWA – CONTRACTOR – RATHJE CONSTRUCTION
WHEREAS, On June 12, 2023, the Project Engineer states the Project construction was completed in general accordance with the approved Plans and Specifications on file with the City of Tiffin, Iowa and placed into operation and recommends Final Payment be made to the Contractor.
WHEREAS, the Original Town Urbanization Project – Phase Two is complete and acceptable to the City of Tiffin,
THEREFORE, BE IT RESOLVED, by the City Council of the City of Tiffin, Iowa, that the Original Town Urbanization Project – Phase Two is complete and acceptable to the City of Tiffin and final payment shall be made to the Contractor.
On the 20th day of June, 2023, at a regular meeting of the Tiffin City Council, Tiffin, Iowa, Councilperson _____ introduced RESOLUTION NO. 2023-045, A RESOLUTION FOR THE COMPLETION AND FINAL ACCEPTANCE OF THE ORIGINAL TOWN URBANIZATION PROJECT – PHASE TWO, TIFFIN, IOWA – CONTRACTOR – RATHJE CONSTRUCTION and made a motion for approval. Motion seconded by Councilperson _____.
Ayes:
Nays:
Absent:
Whereupon _____ Council members were present and voted approval and Mayor Berner declared that RESOLUTION NO. 2023-045, A RESOLUTION FOR THE COMPLETION AND FINAL ACCEPTANCE OF THE ORIGINAL TOWN URBANIZATION PROJECT – PHASE TWO, TIFFIN, IOWA – CONTRACTOR – RATHJE CONSTRUCTION to be adopted and signified his approval of the same by affixing his signature thereto.
Passed by the City Council on the 20th day of June, 2023.
City of Tiffin
______________________________
Steven L. Berner, Mayor
ATTEST: _______________________
Abigail Hora, City Clerk
Sources
- sharepoint (I-3 - Resolution 2023-045 - Final Acceptance of Original Town Urbanization Project Phase Two.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.