K-3 - Change Order 3 - Boomerang - Well 5, Pump, Controls, Watermain
Page 1 of 1
Text from the PDF text layer; check the PDF for anything that matters.June 6, 2023 CHANGE ORDER NO. 3
WELL 5 PUMP, CONTROLS AND WATER MAIN
TIFFIN, IOWA
Change Order No. 3 is for the following modifications to the project:
1. Equipment and labor to evaluate well casing and switch out 8”
Boreline flexible drop pipe and coupling with 6” Boreline flexible
drop pipe and coupling due to issues with installation.
LS $12,557.60
Total: $12,557.60
Change Order No. 3 increases the contract amount by $ 12,557.60 .
BOOMERANG CORP. CITY OF TIFFIN, IOWA
By Keegan Parizek By
Title Project Manager Title
Date 06/06/2023 Date
VEENSTRA & KIMM, INC. ATTEST:
By By
Title Project Engineer Title
Date June 6, 2023 Date
V&K Job No. 5093/1