contract agreement · K-4

K-4 - Pay Estimate 5 - Boomerang - Well 5, Pump, Controls, Watermain

Open the PDF

Page 2 of 2

Text from the PDF text layer; check the PDF for anything that matters.
SUMMARY Total Approved Total Completed Contract Price $ 779,550.00 $ 786,345.46 Approved Change Order (list each) Change Order No. 1 $ 8,052.88 $ 8,052.88 Change Order No. 2 $ 9,081.57 $ 9,081.57 Change Order No. 3 $ 12,557.60 $ 12,557.60 Revised Contract Price $ 809,242.05 $ 816,037.51 Stored $ - Total Earned $ 816,037.51 Retainage (5%) $ 40,801.88 Total Earned Less Retainage $ 775,235.63 Total Previously Approved (list each) Pay Estimate No. 1 $ 210,331.14 Pay Estimate No. 2 $ 131,643.40 Pay Estimate No. 3 $ 270,110.93 Pay Estimate No. 4 $ 54,258.85 Total Previously Approved $ 666,344.32 Percent Complete 100% Amount Due This Request $ 108,891.31 The amount $108,891.31 is recommended for approval for payment in accordance with the terms of the contract. Prepared By: Recommended By: Approved By: Boomerang Corp. Veenstra & Kimm, Inc. Tiffin, Iowa Signature: Keegan Parizek Signature: Signature: Name: Keegan Parizek Name: Dave Schechinger Name: Title: Project Manager Title: Engineer Title: Date: 06/09/2023 Date: June 9, 2023 Date: V&K Job No. 5093/1 2 of 2

Sources

  • sharepoint (K-4 - Pay Estimate 5 - Boomerang - Well 5, Pump, Controls, Watermain.pdf) — where it was found ↗ first seen Oct 12, 2026

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.