contract agreement · K-4
K-4 - Pay Estimate 5 - Boomerang - Well 5, Pump, Controls, Watermain
Page 2 of 2
Text from the PDF text layer; check the PDF for anything that matters. SUMMARY
Total Approved Total Completed
Contract Price $ 779,550.00 $ 786,345.46
Approved Change Order (list each) Change Order No. 1 $ 8,052.88 $ 8,052.88
Change Order No. 2 $ 9,081.57 $ 9,081.57
Change Order No. 3 $ 12,557.60 $ 12,557.60
Revised Contract Price $ 809,242.05 $ 816,037.51
Stored $ -
Total Earned $ 816,037.51
Retainage (5%) $ 40,801.88
Total Earned Less Retainage $ 775,235.63
Total Previously Approved (list each) Pay Estimate No. 1 $ 210,331.14
Pay Estimate No. 2 $ 131,643.40
Pay Estimate No. 3 $ 270,110.93
Pay Estimate No. 4 $ 54,258.85
Total Previously Approved $ 666,344.32
Percent Complete 100% Amount Due This Request $ 108,891.31
The amount $108,891.31 is recommended for approval for payment in accordance with the terms of the contract.
Prepared By: Recommended By: Approved By:
Boomerang Corp. Veenstra & Kimm, Inc. Tiffin, Iowa
Signature: Keegan Parizek Signature: Signature:
Name: Keegan Parizek Name: Dave Schechinger Name:
Title: Project Manager Title: Engineer Title:
Date: 06/09/2023 Date: June 9, 2023 Date:
V&K Job No. 5093/1 2 of 2