contract agreement · K-5
K-5 - Memorandum of Understanding for Setoff
Page 6 of 7
Text read by the vision model; check the PDF for anything that matters.5.2.1.5 Participating Agency submits Debt that is not legally collectable, is unresponsive to IDR requests, or otherwise not compliant with this Agreement.
The right to terminate this Agreement pursuant to this section shall be in addition to and not exclusive of other remedies available to IDR and, notwithstanding any termination, IDR shall be entitled to exercise any other rights and pursue any remedies available under this Agreement, in law, at equity, or otherwise. Participating Agency shall notify IDR in writing if any of the foregoing events occur that would authorize IDR to immediately terminate this Agreement.
5.2.2 Termination for Convenience.
5.2.2.1 Following sixty days written notice, the Participating Agency may terminate this Agreement, in whole or in part, for convenience without the payment of any penalty or incurring any further obligation or liability to Participating Agency. Termination for convenience may be for any reason or no reason at all.
5.2.2.2 Following written notice, IDR may terminate this Agreement, in whole or in part, for convenience without the payment of any penalty or incurring any further obligation or liability to IDR. IDR may further remove all or any portion of Participating Agency’s debt from the State Setoff Program for any or no reason upon written notice. Termination for convenience may be for any reason or no reason at all.
5.2.3 Termination Due to Lack of Funds or Change in Law. Notwithstanding anything in this Agreement to the contrary, either party shall, upon written notice, have the right to terminate this Agreement, in whole or in part, without penalty or liability and without any advance notice as a result of any of the following:
5.2.3.1 The legislature, governor, or other applicable governing body fail, in the sole opinion of the terminating party, to appropriate funds sufficient to allow the terminating party to either meet its obligations under this Agreement or to operate as required and to fulfill its obligations under this Agreement;
5.2.3.2 If funds are de-appropriated, reduced, not allocated, or receipt of funds is delayed, or if any funds or revenues needed by either party to make any payment hereunder are insufficient or unavailable for any other reason as determined by the terminating party in its sole discretion;
5.2.3.3 If the terminating party’s authorization to conduct its business or engage in activities or operations related to the subject matter of this Agreement is withdrawn or materially altered or modified;
5.2.3.4 If the terminating party’s duties, programs, or responsibilities are modified or materially altered; or
5.2.3.5 If there is a decision of any court, administrative law judge, or arbitration panel or any law, rule, regulation, or order is enacted, promulgated, or issued that materially or adversely affects the terminating party’s ability to fulfill any of its obligations under this Agreement.
ARTICLE IV
ADMINISTRATION
6.1 This Agreement does not create a separate legal or administrative entity. Any real, personal, or intellectual property used in this cooperative undertaking shall be acquired, held, and disposed of by the Party which originally obtains, purchases, or develops the property.
6.2 During the Agreement period, the agreement managers shall be contacted on all interpretations and problems relating to the Agreement and shall follow the issues through to their resolution. The agreement managers shall also monitor performance under the Agreement. The Participating Agency agreement manager is identified in Appendix A. The IDR agreement manager is Susan Khamtanh, Procurement Officer, 515-281-5694, [email protected]. Agreement manager contact