K-3 - Pay Estimate 15 - Woodruff Construction - PW Building - Final
Page 3 of 3
Text read by the vision model; check the PDF for anything that matters.<table>
<tr>
<th>A ITEM NO.</th>
<th>B DESCRIPTION OF WORK</th>
<th>C SCHEDULED VALUE</th>
<th>D WORK COMPLETED FROM PREVIOUS APPLICATION (D + E)</th>
<th>E THIS PERIOD</th>
<th>F MATERIALS PRESENTLY STORED (NOT IN D OR E)</th>
<th>G TOTAL COMPLETED AND STORED TO DATE (D+E+F)</th>
<th>H % (G + C)</th>
<th>I BALANCE TO FINISH (C - G)</th>
<th>J RETAINAGE (IF VARIABLE RATE)</th>
</tr>
<tr><td>1</td><td>Mobilization</td><td>$46,750.00</td><td>$46,750.00</td><td>$0.00</td><td></td><td>$46,750.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>2</td><td>General Conditions</td><td>$142,559.00</td><td>$142,559.00</td><td>$0.00</td><td></td><td>$142,559.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>3</td><td>Concrete</td><td>$188,347.00</td><td>$188,347.00</td><td>$0.00</td><td></td><td>$188,347.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>4</td><td>Metals</td><td>$58,436.00</td><td>$58,436.00</td><td>$0.00</td><td></td><td>$58,436.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>5</td><td>Rough Carpentry</td><td>$99,107.00</td><td>$99,107.00</td><td>$0.00</td><td></td><td>$99,107.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>6</td><td>Insulation and Moisture Protection</td><td>$55,773.00</td><td>$55,773.00</td><td>$0.00</td><td></td><td>$55,773.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>7</td><td>Doors, Frames, and Hardware</td><td>$80,489.00</td><td>$80,489.00</td><td>$0.00</td><td></td><td>$80,489.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>8</td><td>Sectional Overhead Doors</td><td>$79,934.00</td><td>$79,934.00</td><td>$0.00</td><td></td><td>$79,934.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>9</td><td>Gypsum Board</td><td>$42,126.00</td><td>$42,126.00</td><td>$0.00</td><td></td><td>$42,126.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>10</td><td>Flooring (carpet, resilient, ceramic tile)</td><td>$25,841.00</td><td>$25,841.00</td><td>$0.00</td><td></td><td>$25,841.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>11</td><td>Acoustical Ceilings</td><td>$12,462.00</td><td>$12,462.00</td><td>$0.00</td><td></td><td>$12,462.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>12</td><td>Painting</td><td>$14,778.00</td><td>$14,778.00</td><td>$0.00</td><td></td><td>$14,778.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>13</td><td>Specialties</td><td>$18,343.00</td><td>$18,343.00</td><td>$0.00</td><td></td><td>$18,343.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>14</td><td>Casework</td><td>$9,634.00</td><td>$9,634.00</td><td>$0.00</td><td></td><td>$9,634.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>15</td><td>Pre-engineered Wood Building</td><td>$498,775.00</td><td>$498,775.00</td><td>$0.00</td><td></td><td>$498,775.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>16</td><td>Fire Suppression</td><td>$93,719.00</td><td>$93,719.00</td><td>$0.00</td><td></td><td>$93,719.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>17</td><td>Mechanical</td><td>$414,689.00</td><td>$414,689.00</td><td>$0.00</td><td></td><td>$414,689.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>18</td><td>Electrical</td><td>$398,374.54</td><td>$398,374.54</td><td>$0.00</td><td></td><td>$398,374.54</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>19</td><td>Earthwork</td><td>$69,343.00</td><td>$69,343.00</td><td>$0.00</td><td></td><td>$69,343.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>20</td><td>Utilities</td><td>$53,991.00</td><td>$53,991.00</td><td>$0.00</td><td></td><td>$53,991.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>21</td><td>Fencing</td><td>$44,620.00</td><td>$44,620.00</td><td>$0.00</td><td></td><td>$44,620.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>22</td><td>Overhead Crane</td><td>$46,861.00</td><td>$46,861.00</td><td>$0.00</td><td></td><td>$46,861.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>23</td><td>Paving</td><td>$66,602.00</td><td>$66,602.00</td><td>$0.00</td><td></td><td>$66,602.00</td><td>100.00%</td><td></td><td></td></tr>
<tr><th colspan="10">CHANGE ORDERS</th></tr>
<tr><td>CO1</td><td>(CAR1,CAR2,CAR4,CAR6)</td><td>$27,695.56</td><td>$27,695.56</td><td>$0.00</td><td></td><td>$27,695.56</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>CO2</td><td>(CAR7,CAR8,CAR10,CAR11)</td><td>$13,661.03</td><td>$13,661.03</td><td>$0.00</td><td></td><td>$13,661.03</td><td>100.00%</td><td></td><td></td></tr>
<tr><td>CO3</td><td>(CAR13, CAR15, CAR16, CAR17, CAR18, CAR19)</td><td>$961.69</td><td>$961.69</td><td>$0.00</td><td></td><td>$961.69</td><td>100.00%</td><td></td><td></td></tr>
<tr><th colspan="10">GRAND TOTALS</th></tr>
<tr><td colspan="2"></td><td>$2,603,871.82</td><td>$2,602,910.13</td><td>$0.00</td><td>$0.00</td><td>$2,603,871.82</td><td>100.00%</td><td>$0.00</td><td>$0.00</td></tr>
</table>