Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
July 28, 2023
PROJECT UPDATE
DEVELOPMENT ASSISTANCE – ANDREW INHELDER
Lotus Hill OPD & The State OPD
MSA provided reviews of the preliminary plats for both developments with no further comments. Comment
regarding sanitary sewer design is remaining. Some comments were made that will be incorporated into the
improvement plans.
Little Clippers Day Care
One outstanding item remaining is a submission of the NPDES
Daytona Estates OPD
Concept plan has been submitted and to be discussed at the Council work session on August 8th. Full OPD site
plan submittal will be submitted after Council work session.
Tiffin Heights West
Revised preliminary plat submitted to MSA on 7/20/23 and are currently under review.
Park Place Part 8
A punch list review was conducted on-site on 6/26/2023 with a summary of items identified sent out to the
developer. Additionally, MSA has reviewed the final plat and has no additional comments on 7/7/2023.
Prairie Village Commercial Part 1, Lot 2
MSA provided review comments to the developer 7/7/23 with follow up answers to some questions regarding
fire lanes on 7/25/23.
Upcoming Projects
Major Upcoming Description Next Steps/Schedule
Infrastructure Project
Wastewater Treatment Improvements The current wastewater treatment facility (WWTF) has a Final Compliance with NPDES
chloride compliance schedule. There is not any wastewater Permit required October 1, 2025.
treatment equipment/processes designed to remove chloride
so typically source control is the only economical means of MSA presented its findings on
meeting compliance. The existing treatment facility is at about November 1st 2022. MSA has
50% capacity. However, if the past growth rate continues an prepared a proposed schedule
expansion will be required in the next 6-8 years. for wastewater treatment, water
treatment and water supply
improvement projects.
Deer View Avenue and Tall Grass DOT has requested concurrence from the City on permanent TBD
Avenue & Hwy 6 Intersection improvements to intersection within 5 years of installation of
Improvements temporary traffic signals in 2020. Scope includes both
pedestrian and vehicle accommodations.
PROJECT UPDATE
Page 2 of 2
Sources
- sharepoint (M-6 - City Engineer's Report.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.