Text from the PDF text layer; check the PDF for anything that matters. PROJECT UPDATE A Review of MSA Projects in Your Community
City of Tiffin, IA
CLIENT LIAISONS:
Andrew Inhelder, PE / Jake Huck, P.E.
Office: 319.364.4773
Cell(s): 515.802.0906/ 563.542.6571
[email protected] / [email protected]
DATE:
August 31, 2023
ON-GOING PROJECTS
North Park Road Improvements – James Watters
MSA has submitted a request to the IaDOT for application to the TSIP funding program. Expecting response
from DOT on project suitability in September.
MSA is inquiring with DOT personnel on applicability of project for Statewide Transportation Alternative
Program (TAP) funding and the Iowa Clean Air Attainment Program (ICAAP) funding.
MSA is awaiting decision from the City and School District regarding whether to incorporate roundabout
concept, submitted to City in May 2023, into project plans.
Highway 6 Concept and Cost Estimate – Ben Wilkinson
MSA has completed our conceptual design of the project and is finalizing the cost estimate and cost sharing
estimate. MSA will reach out to the City to schedule a meeting in the near future. The DOT is discussing
internally with their structures group to determine recommendations. After meeting with the City, a meeting
with the DOT can be scheduled.
Comprehensive Water System Evaluation – Clint Wienen
The RO pilot is scheduled to conclude on September 6th. MSA will complete the preliminary engineering report
once the reverse osmosis pilot report is received from Harn.
Trail Connection between Roundabout and Parking Lot – Andrew Inhelder
Storm water calculations have been completed for this project in conjunction with the North Park Road storm
water calculations since the trail project lies within the same floodplain as the southern portion of North Park
Road. The plans are nearing 75% complete. Currently working with Bella Sala to determine allowable grading
near their existing sign on the SE side of the intersection. Once agreement has been reached on the sign, plans
will be finalized and sent out for bidding.
PROJECT UPDATE
Page 1 of 3