K-2 - Change Order 1 - Boomerang - Potter Creek Interceptor Sewer
Page 1 of 3
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 12/1/2023
Change Order No: 1 (ONE)
Agreement Date: 7/6/2023
PROJECT: Potter Creek Interceptor Sewer Project #21218.244
OWNER: Tiffin, IA
CONTRACTOR: Boomerang Corp
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Change pipe material to regular joint C-900 PVC pipe outside of cased roadway crossing areas.
Reduce Item #5 San. Sewer, Trenched, 12-inch Dia. RJ -265LF @ $140.00 $ -37,100.00
Add Item #35 San. Sewer, Trenched, 12-inch Dia. C-900 PVC 265LF @ $126.00 $ 33,390.00
Estimated Total $ -3,710.00
Sanitary service to duplex #652/654 Croell Ave. crosses new sewer trench. The City requested that this service be connected to the new sewer. See RFC#1.
Wet, possible unsuitable native soils have been found during trench excavation. The material will be extremely difficult to obtain proper trench compaction, given current weather conditions. Replacement of this soil with sand backfill is recommended. See RFC #2.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $ 1,067,837.60
CONTRACT with LAST CHANGE ORDER: $ 1,067,837.60
THIS CHANGE ORDER AMOUNT: $ 5,439.80
NEW CONTRACT PRICE: $ 1,073,277.40
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): N/A
NEW Completion Date: N/A
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER:
CONTRACTOR: See Attachments for signatures
ENGINEER: