M-10 - Highway 6 Widening Project Schedule
Page 1 of 1
Text read by the vision model; check the PDF for anything that matters.<table>
<tr>
<th>Task</th>
<th>Dur.</th>
<th>Start</th>
<th>End</th>
<th>Responsible</th>
<th>Notes</th>
</tr>
<tr>
<td>STP-006-7(098)-2C-52</td>
<td></td>
<td></td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>D00 - Pre-Design Concept</td>
<td>126</td>
<td>7/28/2023</td>
<td>12/1/2023</td>
<td>DOT</td>
<td>MSA completed conceptual design and cost estimate</td>
</tr>
<tr>
<td>W00 - Preliminary Wetland Review</td>
<td>32</td>
<td>2/12/2024</td>
<td>3/15/2024</td>
<td>DOT - LEB</td>
<td>M. Sloppy</td>
</tr>
<tr>
<td>D01 - Survey Plan and Photogrammetry (DTM)</td>
<td>151</td>
<td>10/2/2023</td>
<td>3/1/2024</td>
<td>MSA</td>
<td>M. Harle to confirm with Prelim. Design. Assume DOT review only.</td>
</tr>
<tr>
<td>TE0 - Desktop Review</td>
<td>32</td>
<td>2/12/2024</td>
<td>3/15/2024</td>
<td>DOT - LEB</td>
<td>B. Struecker. Review tree clearing needs ahead of D02</td>
</tr>
<tr>
<td>U00 - Preliminary Utility Review</td>
<td>32</td>
<td>2/12/2024</td>
<td>3/15/2024</td>
<td>MSA / City</td>
<td></td>
</tr>
<tr>
<td>D02 - Design Field Exam</td>
<td>101</td>
<td>1/23/2024</td>
<td>5/3/2024</td>
<td>MSA</td>
<td>Should be held not too long after 5/3. May be able to compress D02-D05</td>
</tr>
<tr>
<td>D03 - Plans for Preliminary Bridge</td>
<td>59</td>
<td>4/9/2024</td>
<td>6/7/2024</td>
<td>MSA</td>
<td></td>
</tr>
<tr>
<td>H00 - Cultural Resources Assessment</td>
<td>101</td>
<td>2/27/2024</td>
<td>6/7/2024</td>
<td>DOT - LEB</td>
<td>J. Bacon. Anticipate need for H01/H03 events</td>
</tr>
<tr>
<td>H06 - SHPO-State Historic Preservation Officer</td>
<td>0</td>
<td>6/7/2024</td>
<td>6/7/2024</td>
<td>DOT - LEB</td>
<td>J. Bacon</td>
</tr>
<tr>
<td>A01 - Approval of DOT Commission - Inclusion in 5-Year Program</td>
<td>0</td>
<td>6/11/2024</td>
<td>6/11/2024</td>
<td>DOT</td>
<td></td>
</tr>
<tr>
<td>NE10 - PCE</td>
<td>39</td>
<td>5/20/2024</td>
<td>6/28/2024</td>
<td>DOT- LEB</td>
<td>C. Schwake. Preliminary review of resources sent 3/13.</td>
</tr>
<tr>
<td>B02 - Drainage Design and Miscellaneous Layout to Office of Design</td>
<td>38</td>
<td>7/30/2024</td>
<td>9/6/2024</td>
<td>MSA</td>
<td>A B01 event should also be added, which will also be MSA, DOT review</td>
</tr>
<tr>
<td>U02 - Project Notification to Utilities</td>
<td>91</td>
<td>6/7/2024</td>
<td>9/6/2024</td>
<td>MSA / City</td>
<td></td>
</tr>
<tr>
<td>D05 - Plans to Right Of Way</td>
<td>74</td>
<td>7/22/2024</td>
<td>10/4/2024</td>
<td>MSA</td>
<td>Keep this date on track</td>
</tr>
<tr>
<td>F03 - Final Regulated Materials Review</td>
<td>207</td>
<td>4/8/2024</td>
<td>11/1/2024</td>
<td>DOT - LEB</td>
<td>B. Azeltine</td>
</tr>
<tr>
<td>U03 - 1st Plan Submittal to Utilities</td>
<td>91</td>
<td>11/8/2024</td>
<td>2/7/2025</td>
<td>MSA / City</td>
<td></td>
</tr>
<tr>
<td>P09 - Public Information Meeting (PIM)</td>
<td>0</td>
<td>3/5/2025</td>
<td>3/5/2025</td>
<td>DOT - District</td>
<td>M. Harle will clear event date. MSA/City to host Public Meeting with DOT</td>
</tr>
<tr>
<td>W02 - Wetland Field Work</td>
<td>63</td>
<td>8/3/2025</td>
<td>10/3/2025</td>
<td>DOT - LEB</td>
<td>M. Sloppy</td>
</tr>
<tr>
<td>S03 - Soils Design Complete</td>
<td>252</td>
<td>3/28/2025</td>
<td>12/5/2025</td>
<td>????</td>
<td></td>
</tr>
<tr>
<td>W04 - 404 Permit Clearance</td>
<td>0</td>
<td>4/17/2026</td>
<td>4/17/2026</td>
<td>DOT - LEB</td>
<td>M. Sloppy</td>
</tr>
<tr>
<td>W03 - 404 Permit Submittal</td>
<td>0</td>
<td>2/20/2026</td>
<td>2/20/2026</td>
<td>DOT - LEB</td>
<td>M. Sloppy</td>
</tr>
<tr>
<td>P08 - Pre-Construction Agreement</td>
<td>0</td>
<td>6/19/2026</td>
<td>6/19/2026</td>
<td>DOT - District / LS</td>
<td>D. Heeren</td>
</tr>
<tr>
<td>DM5 - Design Methods Turn-In</td>
<td>0</td>
<td>6/30/2026</td>
<td>6/30/2026</td>
<td>MSA</td>
<td></td>
</tr>
<tr>
<td>U10 - Utility clearance</td>
<td>0</td>
<td>8/4/2026</td>
<td>8/4/2026</td>
<td>MSA / City</td>
<td></td>
</tr>
<tr>
<td>D08 - Final Grade and Pave Plans</td>
<td>162</td>
<td>2/23/2026</td>
<td>8/4/2026</td>
<td>MSA</td>
<td>Turn-in to Contracts.</td>
</tr>
<tr>
<td>L03 - Letting-Combination Grade and Pave</td>
<td>0</td>
<td>10/20/2026</td>
<td>10/20/2026</td>
<td>DOT Contracts</td>
<td></td>
</tr>
<tr>
<td>C02 - Construction Period (Field Work)</td>
<td>394</td>
<td>10/21/2026</td>
<td>11/19/2027</td>
<td>DOT Construction</td>
<td></td>
</tr>
<tr>
<td>B01</td>
<td></td>
<td></td>
<td></td>
<td>MSA</td>
<td>Needs to be added to the project schedule</td>
</tr>
<tr>
<td>R-events</td>
<td></td>
<td></td>
<td></td>
<td>DOT-ROW</td>
<td>N. Cuva. These need to be added to the project schedule</td>
</tr>
<tr>
<td>T01 and T02</td>
<td></td>
<td></td>
<td></td>
<td>MSA</td>
<td>MSA has done boundary survey and will complete plats.</td>
</tr>
</table>