M-10 - Schedule - Kimberlite Improvements - 4-8-24
Page 1 of 1
Text from the PDF text layer; check the PDF for anything that matters.ID Task Task Name Duration Start Finish Predecessors Resource Names Apr 14, '24 Apr 21, '24 Apr 28, '24 May 5, '24 May 12, '24 May 19, '24 May 26, '24 Jun 2, '24
Mode M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
1 Tiffin Kimberlite Street 90 days Mon 4/15/24Fri 8/16/24
2 Start Date 0 days Mon 4/15/24Mon 4/15/24 4/15
3 Traffic Control 1 day Mon 4/15/24Mon 4/15/242 ATC ATC
4 Erosion Control 1 day Tue 4/16/24 Tue 4/16/24 3 Stevens Stevens
5 Removals 2 days Wed 4/17/24Thu 4/18/24 4 AACI AACI
6 Grading 7 days Fri 4/19/24 Mon 4/29/245 AACI AACI
7 Subdrains 2 days Tue 4/30/24 Wed 5/1/24 6 AACI AACI
8 Subbase 2 days Thu 5/2/24 Fri 5/3/24 7 AACI AACI
9 Paving 10 days Mon 5/6/24 Fri 5/17/24 8 AACI AACI
10 Asphalt 3 days Mon 5/20/24Wed 5/22/249 Hansen Hansen
11 Sidewalks 4 days Thu 5/23/24 Tue 5/28/24 10 AACI AACI
12 Backfill 3 days Wed 5/29/24Fri 5/31/24 11 AACI AACI
13 Pavement Markings 1 day Mon 6/3/24 Mon 6/3/24 12 ATC ATC
14 Seeding 2 days Thu 8/15/24 Fri 8/16/24 13 Stevens
Task Project Summary Manual Task Start-only Deadline
Project: Schedule 040524 DRAF Split Inactive Task Duration-only Finish-only Progress
Date: Mon 4/8/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone
Page 1