contract agreement · E-10
Approval of Change Order #19 – Boomerang Corp. – North Park Road Improvements Project — E-10
Page 3 of 5
Text from the PDF text layer; check the PDF for anything that matters. 8280: Boomerang failed to adequately protect Item 0130 Median, PCC, 6" from STA 223+57 to 227+85 from rain damage. Burlap & plastic were not added to the surface until
after rain began and rain damage was sustained on the plastic concrete. Remediation includes a price adjustment per Case I in CM 2.53.
C-Settlement for cost(s) of change
8280: Agreed unit price reduction of 5% per Case I in CM 2.53. 0130 Contract Unit Price of $43.00/SY x 5% = $2.15/SY price adjustment x 304.20 SY = ($654.03) Each.
D-Justification for cost(s)
8280: Per adjustment schedule in CM 2.53 (Case I)
New Items
Line Number Item ID Unit Quantity Unit Price Extension
Section: 0001 - STP-U-7662(615)--70-52, ROADWAY ITEMS
8280 6200-5000041 EACH 304.200 -$2.150 -$654.03
{PRICE ADJUSTMENT} RAIN DAMAGED PORTLAND CEMENT CONCRETE PAVEMENT (BY GUIDE SCHEDULE - CONSTRUCTION MANUAL 2.53)
Reason: $2.15 is 5% of the Median unit price of $43.00. Per CM 2.53 Case I, 95% will be paid out with a 5% price reduction. Quantity of damaged median was 304.2SY.
Funding Details
52-7662-615-CAT-1 ROADWAY ITEMS 304.200 -$2.150 -$654.03
Change Order Details: 09/23/2026
52-7662-615 Page 2 of 3
Sources
- revize: E-10 (BHkTtg0cFCBQro542tfY2VwfahHv2D.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-10 Approval of Change Order #19 – Boomerang Corp. – North Park Road Improvements Project
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.