K-3 - Change Order 1 - Rathje Construction - Original Town Phase 3
Page 1 of 2
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 2, August, 2024
Change Order No: 1 (ONE)
Agreement Date: 12/14/2023
PROJECT: Original Town Urbanization – Phase 3 HFC #18218.131
OWNER: Tiffin, IA
CONTRACTOR: Rathje Construction Co.
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Unstable subgrade materials have been encountered on the project. An additional 6-inches of subbase material with geogrid is recommended, similar to the work on the Phase Two project. See attachment for details.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $2,134,856.90
CONTRACT with LAST CHANGE ORDER: $2,134,856.90
THIS CHANGE ORDER AMOUNT: $36,819.89
NEW CONTRACT PRICE: $2,1871,676.79
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): 8 Days
NEW Completion Date: September 13, 2025
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER: ________________________________
CONTRACTOR: See Attached
ENGINEER: ________________________________