engineering report · M-9
M-9 - City Engineer Report
Page 3 of 4
Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin
September 27, 2024
PROJECT UPDATE
DEVELOPMENT ASSISTANCE – ANDREW INHELDER
NO FURTHER COMMENTS
Development Name Description
Lotus Hill – Andersen Addition OPD No further comments.
Daytona Estates OPD No further comments
UPN Network Routing – Hwy 6 & Kimberlite No further comments.
to Hwy 6 & Croell
Park Place City Center – Part Two, Phase Nine No further comments.
Veritas Church Parking Expansion No further comments.
The States – Andersen Addition OPD No further comments.
Park Place City Center, Lot 8 No further comments.
Tiffin West ON Site No further comments (OFF site plans have not been
completed review).
UNDER CONSTRUCTION
Development Name Description
Hawk Wash Detention basin has been regraded and reseeded in areas
where erosion was forming. Once grass has established site
will be in compliance with plans.
Kimberlite Street South Site has been reseeded.
Park Place City Center, Lot 8 MSA is performing observations for this project for the public
improvement portion.
Tiffin West ON Site MSA is performing observations for this project. Water main
is complete and has passed testing. Sanitary sewer is installed
pending testing. Storm sewer has begun installation. Road bed
grading has begun.
Tiffin Heights West IDOT Utility Extension – MSA is performing observations for this project. Water main
Along Hwy 6 from Deer View to Half Moon along Hwy 6 has passed testing, water main north along Half
Ave Moon pending testing. Sanitary sewer to begin next along Hwy
6.
AWAITING RESUBMISSION
Development Name Description
Prairie Village Commercial Part 1, Lot 2 Review comments sent 7/25/23. Awaiting resubmission.
Potential Site Plan NE – Responded to questions 11/2/23. Awaiting submission for
Tiffin West Development review.
Tiffin Heights West Review comments sent 8/13/24. Awaiting resubmission.
Casey’s in Tiffin West Lot 1 Review comments sent 7/30/24. Awaiting resubmission.
Kimberlite North of Hwy 6 Connection City, Developer, MSA, and DOT met on 8/22/24 to discuss
steps moving forward. Developer to submit proposed
improvements for review.
IN REVIEW
Development Name Description
Village Drive Extension (By water tower) Revised plans & drainage report submitted 9/23/24, currently
in review.
Tiffin West OFF Site Plans Revised plans submitted 9/25/24, currently in review.
PROJECT UPDATE
Page 3 of 4
Sources
- sharepoint (M-9 - City Engineer Report.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.