contract agreement · E-10
Approval of Change Order #19 – Boomerang Corp. – North Park Road Improvements Project — E-10
Page 1 of 5
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # E-10
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: October 1, 2026
AGENDA ITEM: Approval of Change Order #19 – Boomerang Corp. – North Park Road
Improvements Project
ACTION: Motion
Background
The City of Tiffin's STP-U-7662(615)--70-52 project was awarded to Boomerang Corp. The
project was let on December 17, 2024.
Change Order No. 19 is identified as a non-substantial change order and was created on
September 18, 2026. The purpose of the change order is to address a price adjustment associated
with rain damage to median pavement during construction.
The change order addresses Item 0130 – Median, P.C. Concrete, 6", located from approximately
Station 223+57 to Station 227+85.
According to the change order documentation, Boomerang Corp. did not adequately protect the
newly placed median pavement from rain. Burlap and plastic were not added to the surface until
after the rain began, and the plastic concrete sustained rain damage.
Rather than requiring replacement of the affected pavement, the contract's adjustment provisions
provide for a price reduction based on the extent of the damage.
The change order has been reviewed through the project's Doc Express process. Boomerang
Corp. electronically approved the change order on September 24, 2026, and MSA Professional
Services electronically recommended/approved the change order on September 25, 2026.
Recommendation
Staff recommends approval of Change Order No. 19 with Boomerang Corp., resulting in a
$654.03 reduction to the authorized project amount and establishing a revised project amount of
$5,586,322.65.
ATTACHMENTS: Change Order
1
Sources
- revize: E-10 (BHkTtg0cFCBQro542tfY2VwfahHv2D.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-10 Approval of Change Order #19 – Boomerang Corp. – North Park Road Improvements Project
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.