contract agreement · K-4
K-4 - Change Order 2 - Original Town Phase 3 - Rathje Construction
Page 1 of 2
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER
DATE: 11 Nov, 2024
Change Order No: 2 (TWO)
Agreement Date: 12/14/2023
PROJECT: Original Town Urbanization – Phase 3 HFC #18218.131
OWNER: Tiffin, IA
CONTRACTOR: Rathje Construction Co.
DESCRIPTION OF CHANGES TO CONTRACT DOCUMENTS:
Additional work includes additional tree removal, additional concrete work, and additional drainable backfill along retaining wall. See attachment for details.
CONTRACT PRICE CHANGES:
Original CONTRACT PRICE: $ 2,134,856.90
CONTRACT with LAST CHANGE ORDER: $ 2,171,676.79
THIS CHANGE ORDER AMOUNT: $ 20,400.00
NEW CONTRACT PRICE: $ 2,192,076.79
CONTRACT TIME CHANGES
CONTRACT TIME (increased)(decreased): 2.5 Days
NEW Completion Date: September 16, 2025
APPROVALS REQUIRED: To be effective this Order must be approved by the OWNER.
OWNER:
CONTRACTOR: See Attached
ENGINEER: