resolution · J-2
J-2 - Resolution 2024-076 - Honey Lane Development Developer's Agreement - Tiffin West
Dated December 17, 2024City Council — regular meeting, December 17, 2024 13 pages
Res. 2024-076, Res. 2024-075
Page 5 of 13
Text read by the vision model; check the PDF for anything that matters.requirements of the Tiffin Design Standards, currently found in Chapter 16. This includes, but is not limited to, entering into appropriate fence agreements prior to final plat approval, as approved by the City.
H. Offsite Improvements. Certain offsite improvements are necessary for this subdivision and must be completed prior to final plat approval, as determined by the City, which includes the widening of Roberts Ferry Road from approximately 500 feet south to approximately 475 feet north of the intersection of Village Drive. This includes but is not limited to, full depth HMA widening, mill and overlay of the existing roadway pavement, installation of PCC curb and gutter and pavement where necessary, traffic control, signage and pavement markings, installation of conduit for future signal, sidewalk crossing improvements, and associated grading to maintain drainage in the area as identified in the approved plans.
I. Village Drive. Village Drive shall be completed as shown on the preliminary plat within two years of the approval of this Agreement. Temporary Turnaround Easements may be required with any final plat approval as determined by the City.
SECTION 4. PUBLIC UTILITIES
Developer agrees that it will obtain any necessary concurrence of utility or other easements from appropriate utility companies. Developer agrees that it will provide for the continuation of all required water, sanitary sewer and storm drainage facilities. The Developer agrees that it will connect and use existing public water supplies in accordance with the Tiffin Municipal Code and that the Developer will provide a plan outlining the drainage of the land and indicating the manner in which the drainage will be accommodated and will connect to the existing storm water sewer systems when available in accordance with the plan approved by the City Engineer.
SECTION 5. EROSION CONTROL AND GRADING
A. Erosion Control. Developer shall design and implement an erosion control plan which shall be reviewed and approved by the City. All areas disturbed by the excavation and backfilling operations shall be reseeded forthwith after the completion of the work in that area. All seeded areas shall be fertilized, mulched and disc anchored as necessary for seed retention. The parties recognize that time is of the essence in controlling erosion, and, if the Developer does not comply with the erosion control plan or any supplementary instructions received from the City, the City may take such action as it deems appropriate to control erosion and assess the costs of such action to the Developer or the property, or both. The City will endeavor to notify the Developer in advance of any proposed action, but failure of the City to do so will not affect the Developer’s and City’s rights or obligations hereunder.
B. Grading. Upon request of the City, the Developer shall provide the City with an “as-constructed” grading plan and a certification by registered land surveyor or engineer that all ponds, swales and ditches, if any, have been constructed in accordance with the plans approved by the City.